ReNews Pakistan is a dedicated digital news platform focused exclusively
on real estate, urban development, infrastructure, and property markets
across Pakistan. It delivers timely updates, policy developments, market
insights, and ground realities shaping the country's land and housing sector.
The platform is structured into
news categories, regional coverage, corporate updates,
and research-based analysis to ensure accurate,
transparent, and sector-specific reporting.
Share Real Estate news, development updates, project information, photographs, videos, or data related to Bajaur District with RE News Pakistan at
mail@renews.pk
View All District Coordinators
For local coordination and district updates, you may also contact our District Coordinator in Bajaur District.
District Coordinator
Coordinator Required
Portfolio will be available soon.
District Guide
Explore quick links and local highlights for Bajaur District.
Bajaur District is situated in Malakand Division, Khyber Pakhtunkhwa, Pakistan. It borders Afghanistan and the districts of Mohmand and Dir, and is known for its mountainous terrain, tribal history, and strategic border location.
KP Solar Power Project in Bajaur Remains Incomplete Despite 2019 Launch
باجوڑ میں 2019 میں شروع ہونے والا سولر پاور منصوبہ تاحال نامکمل
▫️PEDO cites shortage of funds, transmission line issues, local resistance and drainage problems as key hurdles
▫️پیڈو نے فنڈز کی کمی، ٹرانسمیشن لائن، مقامی مزاحمت اور نکاسی آب کے مسائل کو بڑی رکاوٹیں قرار دے دیا
Bajaur: [ReNews Pakistan] A solar power project launched in 2019 to provide affordable and uninterrupted electricity to Khar Bazaar in...
Bajaur: [ReNews Pakistan]
A solar power project launched in 2019 to provide affordable and uninterrupted electricity to Khar Bazaar in Bajaur remains incomplete and non operational, despite missing its original 2024 completion deadline.
The Pakhtunkhwa Energy Development Organisation launched the mini solar grid station under a broader plan to set up nine similar projects in the merged districts, where residents and business communities have long faced electricity shortages and unreliable power supply.
The initiative is being financed through the Khyber Pakhtunkhwa Annual Development Programme. The overall cost of the schemes is estimated at around Rs 575 million, while the Khar Bazaar solar power project alone is valued at approximately Rs 40 million.
According to sources, the 175kV solar grid station includes 324 solar panels, a boundary wall and a control room. Although most of the civil and technical work has reportedly been completed, the project has yet to become operational nearly two years after its expected completion period.
A PEDO official said the project remains inactive due to a shortage of funds required for laying a one kilometre transmission line. The official also said local resistance over the proposed route of the transmission line has further delayed progress.
Officials said drainage problems have also created serious technical concerns at the site. Nearby road construction reportedly lowered the site level, causing water accumulation around the solar installation and creating a risk to the infrastructure.
The PEDO official said additional funding and formal approval are required to adjust or relocate parts of the installation before the project can be safely activated. The official added that these issues must be resolved to protect the solar panels and related equipment from possible damage.
Once the project becomes functional, PEDO will operate the solar grid station for two years before handing it over to a local management committee. The committee is expected to include representatives of the district administration and Khar Bazaar traders.
Local traders have expressed frustration over the repeated delays, saying they have raised the issue with relevant authorities several times but no practical progress has been made. They said the continued lack of reliable electricity is affecting business activity in the bazaar and increasing difficulties for shopkeepers.
District officials said a meeting held in February 2026 resulted in an agreement to begin leveling the project site, resolve drainage problems and move forward with an alternative route for the transmission line.
However, officials acknowledged that minor technical and administrative hurdles are still delaying the full operation of the project.
The prolonged delay has raised concern among residents and traders, who have urged the provincial government and relevant departments to expedite the remaining work and make the long-awaited solar grid station functional without further setbacks.
باجوڑ: [ری نیوز پاکستان]
باجوڑ کے خار بازار کو سستی اور بلا تعطل بجلی فراہم کرنے کے لیے 2019 میں شروع کیا گیا سولر پاور منصوبہ تاحال نامکمل اور غیر فعال ہے، حالانکہ اس کی اصل تکمیل کی مدت 2024 میں ختم ہو چکی تھی۔
پختونخوا انرجی ڈویلپمنٹ آرگنائزیشن (پیڈو) نے یہ منی سولر گرڈ سٹیشن ضم شدہ اضلاع میں ایسے 9 منصوبے قائم کرنے کے وسیع منصوبے کے تحت شروع کیا تھا، جہاں شہریوں اور کاروباری طبقے کو طویل عرصے سے بجلی کی قلت اور غیر یقینی سپلائی کا سامنا ہے۔
یہ منصوبہ خیبر پختونخوا کے سالانہ ترقیاتی پروگرام کے تحت فنانس کیا جا رہا ہے۔ مجموعی سکیموں کی لاگت تقریباً 57 کروڑ 50 لاکھ روپے بتائی گئی ہے، جبکہ صرف خار بازار سولر پاور منصوبے کی مالیت تقریباً 4 کروڑ روپے ہے۔
ذرائع کے مطابق 175 کے وی سولر گرڈ سٹیشن میں 324 سولر پینلز، باؤنڈری وال اور کنٹرول روم شامل ہیں۔ اگرچہ سول اور تکنیکی کام کا بڑا حصہ مکمل ہو چکا ہے، تاہم منصوبہ اپنی متوقع تکمیل کی مدت کے تقریباً دو سال بعد بھی آپریشنل نہیں ہو سکا۔
پیڈو کے ایک افسر کے مطابق منصوبہ ایک کلو میٹر طویل ٹرانسمیشن لائن بچھانے کے لیے درکار فنڈز کی کمی کے باعث غیر فعال ہے۔ افسر نے بتایا کہ ٹرانسمیشن لائن کے مجوزہ روٹ پر مقامی مزاحمت نے بھی پیش رفت کو مزید متاثر کیا ہے۔
حکام کے مطابق منصوبے کی سائٹ پر نکاسی آب کے مسائل بھی سنگین تکنیکی خدشات پیدا کر رہے ہیں۔ قریبی سڑک کی تعمیر کے باعث سائٹ کی سطح نیچے ہو گئی ہے، جس سے سولر تنصیب کے ارد گرد پانی جمع ہو رہا ہے اور انفراسٹرکچر کو نقصان پہنچنے کا خدشہ ہے۔
پیڈو افسر نے کہا کہ منصوبے کو محفوظ طور پر فعال کرنے سے قبل تنصیب کے بعض حصوں کو ایڈجسٹ یا منتقل کرنے کے لیے اضافی فنڈز اور باقاعدہ منظوری درکار ہے۔ ان کے مطابق سولر پینلز اور متعلقہ آلات کو ممکنہ نقصان سے بچانے کے لیے ان مسائل کا حل ضروری ہے۔
منصوبہ فعال ہونے کے بعد پیڈو دو سال تک سولر گرڈ سٹیشن چلائے گا، جس کے بعد اسے مقامی مینجمنٹ کمیٹی کے حوالے کیا جائے گا۔ اس کمیٹی میں ضلعی انتظامیہ اور خار بازار کے تاجروں کے نمائندے شامل ہونے کی توقع ہے۔
مقامی تاجروں نے بار بار تاخیر پر مایوسی کا اظہار کرتے ہوئے کہا ہے کہ وہ یہ معاملہ متعلقہ حکام کے سامنے کئی مرتبہ اٹھا چکے ہیں، مگر عملی پیش رفت نہیں ہو سکی۔ تاجروں کے مطابق بجلی کی قابل اعتماد فراہمی نہ ہونے سے بازار کی کاروباری سرگرمیاں متاثر ہو رہی ہیں اور دکانداروں کی مشکلات میں اضافہ ہو رہا ہے۔
ضلعی حکام کا کہنا ہے کہ فروری 2026 میں ہونے والے ایک اجلاس میں منصوبے کی سائٹ کو لیول کرنے، نکاسی آب کے مسائل حل کرنے اور ٹرانسمیشن لائن کے متبادل روٹ پر کام آگے بڑھانے پر اتفاق کیا گیا تھا۔
تاہم حکام نے تسلیم کیا کہ بعض معمولی تکنیکی اور انتظامی رکاوٹیں اب بھی منصوبے کے مکمل آپریشنل ہونے میں تاخیر کا باعث بن رہی ہیں۔
طویل تاخیر نے مقامی رہائشیوں اور تاجروں میں تشویش پیدا کر دی ہے، جنہوں نے صوبائی حکومت اور متعلقہ محکموں سے مطالبہ کیا ہے کہ باقی ماندہ کام جلد مکمل کر کے طویل عرصے سے منتظر سولر گرڈ سٹیشن کو مزید تاخیر کے بغیر فعال بنایا جائے۔