Construction Projects Face Rising Costs and Delays Due to Slow Approvals, Global Survey Finds
دنیا بھر میں تعمیراتی منصوبوں کی منظوریوں میں تاخیر، لاگت اور مدت میں اضافے کا انکشاف
▫️ Survey of 1,728 construction professionals across 14 countries reveals that approval delays can extend project timelines by more than a month
Dubai | ReNews PakistanConstruction projects worldwide are facing growing challenges as slow approvals, fragmented documentation and administrative bottlenecks contribute to delays, rising costs and difficulties in meeting completion dea...
Dubai | ReNews Pakistan
Construction projects worldwide are facing growing challenges as slow approvals, fragmented documentation and administrative bottlenecks contribute to delays, rising costs and difficulties in meeting completion deadlines.
A global survey conducted by construction and real estate management technology company PlanRadar has highlighted widespread inefficiencies affecting project delivery across Europe, the Middle East and the Asia Pacific region.
The PlanRadar Construction Survey Report 2026 gathered responses from 1,728 construction professionals across 14 countries, including the United Arab Emirates and Saudi Arabia.
According to the findings, nearly three quarters of respondents reported that project approvals and decisions frequently take longer than expected.
Approximately one in four construction professionals said approval delays typically extend project schedules by more than a month.
The report also found that projects experiencing persistent approval delays were more than twice as likely to face delays of at least one month compared with projects where approvals were handled efficiently.
Cost overruns emerged as another major concern. Around two thirds of respondents identified changes introduced during construction as a common cause of budget increases across multiple projects.
These changes may involve design modifications, revised technical requirements or adjustments to project specifications after construction has begun.
The survey further revealed that approximately 80% of professionals reported that at least half of their project documentation was scattered across emails, phone calls, messages and verbal instructions.
Such fragmented communication makes it difficult to track decisions, establish accountability and identify responsibility when disputes or delays occur.
According to the report, 70% of professionals who could easily access project documentation expressed confidence in their ability to demonstrate responsibility for delays or additional costs.
In comparison, only 35% of respondents dealing with poorly organised documentation reported similar confidence.
PlanRadar Co-Founder and Co-CEO Ibrahim Imam said that even relatively minor administrative delays could create significant consequences as construction activity increases.
He emphasised the need for construction companies to improve accountability, streamline approvals and ensure faster access to reliable project information ahead of 2027.
The survey also highlighted the growing importance of digital construction management systems.
Four out of five professionals using centralised digital systems to record project changes reported improvements in their ability to control costs or protect profit margins.
Additionally, 58% of respondents expected artificial intelligence to help reduce workloads associated with project delivery and change management.
The findings also offer lessons for developing construction markets, including Pakistan, where housing project approvals, coordination among contractors, documentation management and timely project completion remain important industry concerns.
The survey was conducted in January 2026, while its findings were highlighted again in October in relation to construction project risks in the UAE.
Pakistan was not separately assessed in the survey, and the results represent respondents' reported experiences rather than direct measurements of all construction projects worldwide.
دبئی | ری نیوز پاکستان
دنیا کے مختلف ممالک میں تعمیراتی منصوبوں کی بروقت تکمیل ایک بڑا چیلنج بن گئی ہے۔ ایک عالمی سروے میں انکشاف ہوا ہے کہ تعمیراتی کام کے دوران ضروری منظوریوں میں تاخیر، غیر منظم دستاویزات اور انتظامی رکاوٹوں کے باعث منصوبوں کی تکمیل میں تاخیر اور تعمیراتی لاگت میں اضافہ ہو رہا ہے۔
تعمیراتی اور رئیل اسٹیٹ منصوبوں کی ڈیجیٹل مینجمنٹ سے متعلق بین الاقوامی کمپنی پلان ریڈار (PlanRadar) کی کنسٹرکشن سروے رپورٹ 2026 میں یورپ، مشرق وسطیٰ اور ایشیا پیسیفک کے 14 ممالک کے 1,728 تعمیراتی ماہرین کی آرا شامل کی گئی ہیں۔ ان میں متحدہ عرب امارات اور سعودی عرب کے ماہرین بھی شامل ہیں۔
رپورٹ کے مطابق تقریباً تین چوتھائی ماہرین نے بتایا کہ تعمیراتی منصوبوں سے متعلق ضروری منظوریوں اور فیصلوں میں اکثر مقررہ مدت سے زیادہ وقت لگتا ہے، جبکہ ہر چار میں سے ایک ماہر کے مطابق منظوریوں میں تاخیر منصوبوں کی تکمیل میں عموماً ایک ماہ سے زیادہ اضافے کا باعث بنتی ہے۔
سروے میں یہ بات بھی سامنے آئی کہ جن منصوبوں میں منظوریوں کی تاخیر مسلسل مسئلہ بنی رہتی ہے، وہاں ایک ماہ یا اس سے زیادہ تاخیر کا امکان ایسے منصوبوں کے مقابلے میں دو گنا سے بھی زیادہ ہوتا ہے جہاں منظوریوں کا عمل بروقت مکمل کیا جاتا ہے۔
رپورٹ کے مطابق دو تہائی جواب دہندگان نے بتایا کہ تعمیراتی کام شروع ہونے کے بعد ڈیزائن، تکنیکی ضروریات یا دیگر امور میں ہونے والی تبدیلیاں ان کے متعدد منصوبوں میں بجٹ بڑھنے کی عام وجہ بنتی ہیں۔
سروے میں تقریباً 80 فیصد ماہرین نے بتایا کہ ان کے منصوبوں کی کم از کم نصف دستاویزات ای میلز، فون کالز، پیغامات اور زبانی ہدایات جیسے مختلف ذرائع میں بکھری ہوتی ہیں۔ اس صورتحال کے باعث کسی فیصلے، تبدیلی یا تاخیر کی ذمہ داری کا تعین مشکل ہو جاتا ہے۔
رپورٹ میں بتایا گیا کہ جن ماہرین کے لیے متعلقہ دستاویزات تلاش کرنا آسان تھا، ان میں سے 70 فیصد کو تاخیر یا اضافی اخراجات کی ذمہ داری ثابت کرنے کی اپنی صلاحیت پر اعتماد تھا، جبکہ غیر منظم ریکارڈ رکھنے والوں میں یہ شرح 35 فیصد رہی۔
پلان ریڈار کے شریک بانی اور شریک چیف ایگزیکٹو ابراہیم امام نے کہا کہ تعمیراتی سرگرمیوں میں اضافے کے ساتھ معمولی انتظامی تاخیر بھی بڑے مسائل پیدا کر سکتی ہے۔ ان کے مطابق 2027 کے دوران تعمیراتی کمپنیوں کو ذمہ داریوں کے واضح تعین، منظوریوں کے بہتر نظام اور متعلقہ معلومات تک فوری رسائی پر توجہ دینا ہوگی۔
سروے کے مطابق تعمیراتی تبدیلیوں کا ریکارڈ رکھنے کے لیے مرکزی ڈیجیٹل نظام استعمال کرنے والے ہر پانچ میں سے چار ماہرین نے منصوبوں کی لاگت قابو میں رکھنے یا منافع کے تحفظ کی صلاحیت میں بہتری کی اطلاع دی۔
اسی طرح 58 فیصد جواب دہندگان نے توقع ظاہر کی کہ مصنوعی ذہانت منصوبوں کی بروقت تکمیل اور تعمیراتی تبدیلیوں کے انتظام سے متعلق کام کا بوجھ کم کرنے میں مدد دے سکتی ہے۔
رپورٹ کے نتائج پاکستان سمیت دیگر ترقی پذیر ممالک کے تعمیراتی شعبوں کے لیے بھی اہمیت رکھتے ہیں، جہاں ہاؤسنگ منصوبوں کی منظوریوں، تعمیراتی تبدیلیوں، ٹھیکیداروں کے درمیان رابطوں اور منصوبوں کی بروقت تکمیل جیسے مسائل موجود ہیں۔
واضح رہے کہ یہ سروے جنوری 2026 میں کیا گیا تھا، جبکہ اکتوبر میں اس کے نتائج کو متحدہ عرب امارات کے تعمیراتی شعبے کے تناظر میں دوبارہ اجاگر کیا گیا۔ رپورٹ میں پاکستان کے منصوبوں کا الگ جائزہ شامل نہیں ہے۔