Audit Flags Rs 25.744 Million in Irregular Payments to Officers Posted Outside Diamer Basha Dam Project
دیامر بھاشا ڈیم منصوبے سے باہر تعینات افسران کو 2 کروڑ 57 لاکھ روپے کی ادائیگی پر آڈٹ اعتراض
▫️لاہور اور اسلام آباد میں تعینات افسران کو منصوبے سے متعلق ذمہ داریاں ادا نہ کرنے کے باوجود ڈیم تعمیراتی فنڈز سے تنخواہیں دی گئیں
Islamabad | ReNews PakistanThe Auditor General of Pakistan has raised serious objections over the payment of Rs 25.744 million in salaries and allowances to officers who were posted outside the Diamer Basha Dam Project (DBDP), describing...
Islamabad | ReNews Pakistan
The Auditor General of Pakistan has raised serious objections over the payment of Rs 25.744 million in salaries and allowances to officers who were posted outside the Diamer Basha Dam Project (DBDP), describing the expenditure as an irregular use of funds earmarked for one of the country's largest hydropower projects.
According to the audit report, the payments were made to officers who neither worked on the Diamer Basha Dam Project nor performed any duties related to its execution. Despite this, they continued to receive salaries and allowances from the project's construction budget, resulting in what the audit termed an unjustified and irregular expenditure.
One of the cases highlighted in the report involves an officer who was assigned the additional charge of General Manager (LA&R/HRD), Wapda, on October 11, 2022. Instead of serving at the project's designated headquarters in Chilas, the officer remained posted in Lahore. The audit further noted that on January 31, 2025, the same officer was reappointed as Advisor (HR & Logistics), even though no such position exists in the approved Project Cycle-I (PC-I) of the Diamer Basha Dam Project. He continued to perform his duties from Lahore rather than the project site.
The audit found that salaries and allowances totaling Rs 25.744 million, including Rs 17.717 million and Rs 8.027 million paid to the officers concerned, were charged to funds allocated for dam construction. It concluded that these expenditures had no justification because the officers were not engaged in project activities.
According to the report, the failure to comply with the approved PC-I and other applicable rules resulted in irregular expenditure up to the financial year 2024-25 through the unauthorized attachment of officers outside the project. The audit emphasized that project funds should only be utilized for positions and activities specifically authorized under the approved PC-I.
The matter was initially taken up with the project management in September 2025 and subsequently reported to the Ministry of Water Resources (MoWR) in December 2025. In its response, the management stated that the officers had been posted with the Chairman's Office in the best interest of the Authority's operations.
The audit, however, rejected this explanation, observing that the officers' postings in Islamabad and Lahore were in clear violation of the provisions of the approved PC-I. It maintained that administrative convenience could not justify charging the salaries of officers serving outside the project to funds specifically allocated for the Diamer Basha Dam Project.
The audit observation, identified as PDP-219/2025-26, was discussed during a meeting of the Departmental Accounts Committee (DAC) held on January 23, 2026. However, according to the report, the Principal Accounting Officer (PAO) of the Ministry of Water Resources did not provide the minutes of the meeting before the audit report was finalized.
In its recommendations, the audit called on the management to immediately discontinue the payment of salaries and allowances of these officers from Diamer Basha Dam Project funds. It further recommended that the entire amount of Rs 25.744 million already paid be recovered from the Coordination Wing of Wapda, which is responsible for meeting the Authority's administrative expenditures rather than charging them to the dam construction project.
The Auditor General of Pakistan has raised serious objections over the payment of Rs 25.744 million in salaries and allowances to officers who were posted outside the Diamer Basha Dam Project (DBDP), describing the expenditure as an irregular use of funds earmarked for one of the country's largest hydropower projects.
According to the audit report, the payments were made to officers who neither worked on the Diamer Basha Dam Project nor performed any duties related to its execution. Despite this, they continued to receive salaries and allowances from the project's construction budget, resulting in what the audit termed an unjustified and irregular expenditure.
One of the cases highlighted in the report involves an officer who was assigned the additional charge of General Manager (LA&R/HRD), Wapda, on October 11, 2022. Instead of serving at the project's designated headquarters in Chilas, the officer remained posted in Lahore. The audit further noted that on January 31, 2025, the same officer was reappointed as Advisor (HR & Logistics), even though no such position exists in the approved Project Cycle-I (PC-I) of the Diamer Basha Dam Project. He continued to perform his duties from Lahore rather than the project site.
The audit found that salaries and allowances totaling Rs 25.744 million, including Rs 17.717 million and Rs 8.027 million paid to the officers concerned, were charged to funds allocated for dam construction. It concluded that these expenditures had no justification because the officers were not engaged in project activities.
According to the report, the failure to comply with the approved PC-I and other applicable rules resulted in irregular expenditure up to the financial year 2024-25 through the unauthorized attachment of officers outside the project. The audit emphasized that project funds should only be utilized for positions and activities specifically authorized under the approved PC-I.
The matter was initially taken up with the project management in September 2025 and subsequently reported to the Ministry of Water Resources (MoWR) in December 2025. In its response, the management stated that the officers had been posted with the Chairman's Office in the best interest of the Authority's operations.
The audit, however, rejected this explanation, observing that the officers' postings in Islamabad and Lahore were in clear violation of the provisions of the approved PC-I. It maintained that administrative convenience could not justify charging the salaries of officers serving outside the project to funds specifically allocated for the Diamer Basha Dam Project.
The audit observation, identified as PDP-219/2025-26, was discussed during a meeting of the Departmental Accounts Committee (DAC) held on January 23, 2026. However, according to the report, the Principal Accounting Officer (PAO) of the Ministry of Water Resources did not provide the minutes of the meeting before the audit report was finalized.
In its recommendations, the audit called on the management to immediately discontinue the payment of salaries and allowances of these officers from Diamer Basha Dam Project funds. It further recommended that the entire amount of Rs 25.744 million already paid be recovered from the Coordination Wing of Wapda, which is responsible for meeting the Authority's administrative expenditures rather than charging them to the dam construction project.
اسلام آباد | ری نیوز پاکستان
آڈیٹر جنرل آف پاکستان نے دیامر بھاشا ڈیم منصوبے سے باہر تعینات افسران کو تنخواہوں اور الاؤنسز کی مد میں 2 کروڑ 57 لاکھ 44 ہزار روپے کی ادائیگی پر سنگین اعتراض اٹھاتے ہوئے اسے ملک کے اہم ترین پن بجلی منصوبوں میں شامل اس منصوبے کے لیے مختص فنڈز کا بے قاعدہ استعمال قرار دیا ہے۔
آڈٹ رپورٹ کے مطابق یہ ادائیگیاں ایسے افسران کو کی گئیں جو نہ تو دیامر بھاشا ڈیم منصوبے پر کام کر رہے تھے اور نہ ہی منصوبے سے متعلق کوئی ذمہ داریاں ادا کر رہے تھے۔ اس کے باوجود انہیں منصوبے کے تعمیراتی بجٹ سے تنخواہیں اور الاؤنسز ادا کیے جاتے رہے، جسے آڈٹ نے بلا جواز اور بے قاعدہ خرچ قرار دیا۔
رپورٹ میں ایک ایسے افسر کے معاملے کی نشاندہی کی گئی ہے جسے 11 اکتوبر 2022 کو جنرل منیجر ایل اے اینڈ آر/ایچ آر ڈی، واپڈا کا اضافی چارج دیا گیا۔ تاہم منصوبے کے مقررہ مقام چلاس میں فرائض انجام دینے کے بجائے وہ لاہور میں تعینات رہے۔ آڈٹ کے مطابق 31 جنوری 2025 کو اسی افسر کو دوبارہ ایڈوائزر ایچ آر اینڈ لاجسٹکس مقرر کیا گیا، حالانکہ دیامر بھاشا ڈیم منصوبے کے منظور شدہ پی سی ون میں ایسی کوئی آسامی موجود نہیں تھی۔ اس کے باوجود وہ منصوبہ سائٹ کے بجائے لاہور ہی سے فرائض انجام دیتے رہے۔
آڈٹ کے مطابق متعلقہ افسران کو مجموعی طور پر 2 کروڑ 57 لاکھ 44 ہزار روپے ادا کیے گئے، جن میں 1 کروڑ 77 لاکھ 17 ہزار روپے اور 80 لاکھ 27 ہزار روپے کی ادائیگیاں شامل ہیں۔ یہ تمام اخراجات ڈیم کی تعمیر کے لیے مختص فنڈز سے چارج کیے گئے۔
رپورٹ میں قرار دیا گیا کہ چونکہ مذکورہ افسران منصوبے کی سرگرمیوں میں شامل نہیں تھے، اس لیے ان کی تنخواہوں اور الاؤنسز کو منصوبے کے اخراجات میں شامل کرنے کا کوئی جواز نہیں تھا۔ آڈٹ نے کہا کہ منظور شدہ پی سی ون اور متعلقہ قواعد کی خلاف ورزی کے نتیجے میں مالی سال 2024-25 تک غیر مجاز طور پر منصوبے سے باہر افسران کی تعیناتی کے باعث بے قاعدہ اخراجات ہوئے۔
رپورٹ کے مطابق یہ معاملہ ابتدائی طور پر ستمبر 2025 میں منصوبہ انتظامیہ کے ساتھ اٹھایا گیا، جبکہ دسمبر 2025 میں اسے وزارت آبی وسائل کو رپورٹ کیا گیا۔ انتظامیہ نے اپنے جواب میں مؤقف اختیار کیا کہ مذکورہ افسران کو اتھارٹی کے مفاد میں چیئرمین آفس کے ساتھ تعینات کیا گیا تھا۔
تاہم آڈٹ نے یہ مؤقف مسترد کرتے ہوئے قرار دیا کہ اسلام آباد اور لاہور میں افسران کی تعیناتیاں منظور شدہ پی سی ون کی صریح خلاف ورزی تھیں۔ آڈٹ کے مطابق انتظامی سہولت یا اتھارٹی کے مفاد کا مؤقف ایسے اخراجات کو جائز قرار نہیں دے سکتا جو مخصوص طور پر دیامر بھاشا ڈیم منصوبے کے لیے مختص فنڈز سے کیے گئے ہوں۔
آڈٹ اعتراض، جسے پی ڈی پی 219/2025-26 کے طور پر درج کیا گیا، پر 23 جنوری 2026 کو ڈیپارٹمنٹل اکاؤنٹس کمیٹی کے اجلاس میں غور کیا گیا۔ تاہم رپورٹ کے مطابق وزارت آبی وسائل کے پرنسپل اکاؤنٹنگ آفیسر نے آڈٹ رپورٹ کی حتمی تیاری تک اجلاس کے منٹس فراہم نہیں کیے۔
آڈٹ نے اپنی سفارشات میں کہا ہے کہ انتظامیہ فوری طور پر ان افسران کی تنخواہوں اور الاؤنسز کی ادائیگی دیامر بھاشا ڈیم منصوبے کے فنڈز سے بند کرے۔ آڈٹ نے مزید سفارش کی ہے کہ پہلے سے ادا کی گئی 2 کروڑ 57 لاکھ 44 ہزار روپے کی مکمل رقم واپڈا کے کوآرڈی نیشن ونگ سے واپس وصول کی جائے، کیونکہ اتھارٹی کے انتظامی اخراجات پورے کرنا اسی ونگ کی ذمہ داری ہے، نہ کہ انہیں ڈیم کے تعمیراتی منصوبے پر چارج کیا جائے۔
آڈیٹر جنرل آف پاکستان نے دیامر بھاشا ڈیم منصوبے سے باہر تعینات افسران کو تنخواہوں اور الاؤنسز کی مد میں 2 کروڑ 57 لاکھ 44 ہزار روپے کی ادائیگی پر سنگین اعتراض اٹھاتے ہوئے اسے ملک کے اہم ترین پن بجلی منصوبوں میں شامل اس منصوبے کے لیے مختص فنڈز کا بے قاعدہ استعمال قرار دیا ہے۔
آڈٹ رپورٹ کے مطابق یہ ادائیگیاں ایسے افسران کو کی گئیں جو نہ تو دیامر بھاشا ڈیم منصوبے پر کام کر رہے تھے اور نہ ہی منصوبے سے متعلق کوئی ذمہ داریاں ادا کر رہے تھے۔ اس کے باوجود انہیں منصوبے کے تعمیراتی بجٹ سے تنخواہیں اور الاؤنسز ادا کیے جاتے رہے، جسے آڈٹ نے بلا جواز اور بے قاعدہ خرچ قرار دیا۔
رپورٹ میں ایک ایسے افسر کے معاملے کی نشاندہی کی گئی ہے جسے 11 اکتوبر 2022 کو جنرل منیجر ایل اے اینڈ آر/ایچ آر ڈی، واپڈا کا اضافی چارج دیا گیا۔ تاہم منصوبے کے مقررہ مقام چلاس میں فرائض انجام دینے کے بجائے وہ لاہور میں تعینات رہے۔ آڈٹ کے مطابق 31 جنوری 2025 کو اسی افسر کو دوبارہ ایڈوائزر ایچ آر اینڈ لاجسٹکس مقرر کیا گیا، حالانکہ دیامر بھاشا ڈیم منصوبے کے منظور شدہ پی سی ون میں ایسی کوئی آسامی موجود نہیں تھی۔ اس کے باوجود وہ منصوبہ سائٹ کے بجائے لاہور ہی سے فرائض انجام دیتے رہے۔
آڈٹ کے مطابق متعلقہ افسران کو مجموعی طور پر 2 کروڑ 57 لاکھ 44 ہزار روپے ادا کیے گئے، جن میں 1 کروڑ 77 لاکھ 17 ہزار روپے اور 80 لاکھ 27 ہزار روپے کی ادائیگیاں شامل ہیں۔ یہ تمام اخراجات ڈیم کی تعمیر کے لیے مختص فنڈز سے چارج کیے گئے۔
رپورٹ میں قرار دیا گیا کہ چونکہ مذکورہ افسران منصوبے کی سرگرمیوں میں شامل نہیں تھے، اس لیے ان کی تنخواہوں اور الاؤنسز کو منصوبے کے اخراجات میں شامل کرنے کا کوئی جواز نہیں تھا۔ آڈٹ نے کہا کہ منظور شدہ پی سی ون اور متعلقہ قواعد کی خلاف ورزی کے نتیجے میں مالی سال 2024-25 تک غیر مجاز طور پر منصوبے سے باہر افسران کی تعیناتی کے باعث بے قاعدہ اخراجات ہوئے۔
رپورٹ کے مطابق یہ معاملہ ابتدائی طور پر ستمبر 2025 میں منصوبہ انتظامیہ کے ساتھ اٹھایا گیا، جبکہ دسمبر 2025 میں اسے وزارت آبی وسائل کو رپورٹ کیا گیا۔ انتظامیہ نے اپنے جواب میں مؤقف اختیار کیا کہ مذکورہ افسران کو اتھارٹی کے مفاد میں چیئرمین آفس کے ساتھ تعینات کیا گیا تھا۔
تاہم آڈٹ نے یہ مؤقف مسترد کرتے ہوئے قرار دیا کہ اسلام آباد اور لاہور میں افسران کی تعیناتیاں منظور شدہ پی سی ون کی صریح خلاف ورزی تھیں۔ آڈٹ کے مطابق انتظامی سہولت یا اتھارٹی کے مفاد کا مؤقف ایسے اخراجات کو جائز قرار نہیں دے سکتا جو مخصوص طور پر دیامر بھاشا ڈیم منصوبے کے لیے مختص فنڈز سے کیے گئے ہوں۔
آڈٹ اعتراض، جسے پی ڈی پی 219/2025-26 کے طور پر درج کیا گیا، پر 23 جنوری 2026 کو ڈیپارٹمنٹل اکاؤنٹس کمیٹی کے اجلاس میں غور کیا گیا۔ تاہم رپورٹ کے مطابق وزارت آبی وسائل کے پرنسپل اکاؤنٹنگ آفیسر نے آڈٹ رپورٹ کی حتمی تیاری تک اجلاس کے منٹس فراہم نہیں کیے۔
آڈٹ نے اپنی سفارشات میں کہا ہے کہ انتظامیہ فوری طور پر ان افسران کی تنخواہوں اور الاؤنسز کی ادائیگی دیامر بھاشا ڈیم منصوبے کے فنڈز سے بند کرے۔ آڈٹ نے مزید سفارش کی ہے کہ پہلے سے ادا کی گئی 2 کروڑ 57 لاکھ 44 ہزار روپے کی مکمل رقم واپڈا کے کوآرڈی نیشن ونگ سے واپس وصول کی جائے، کیونکہ اتھارٹی کے انتظامی اخراجات پورے کرنا اسی ونگ کی ذمہ داری ہے، نہ کہ انہیں ڈیم کے تعمیراتی منصوبے پر چارج کیا جائے۔