Published: August 15, 2026 - 4:48 PM
Railway Station Remodelling Gives Area a New Look, Work Begins on Lahore’s Second Dancing Fountain
ریلوے سٹیشن کی ری ماڈلنگ سے علاقے کو نئی شکل مل گئی، لاہور میں دوسرے ڈانسنگ فاؤنٹین کی تیاری بھی شروع
▫️Escalators installed for elderly visitors at Data Darbar pedestrian underpass; construction of Bhatti Chowk underpass completed as LDA pushes to finish second dancing fountain and protected U turn on Circular Road
Lahore : Riaz Hussain, ReNews PakistanThe Lahore Development Authority (LDA) has completed the remodelling of the parking area in front of Lahore Railway Station along with the installation of a dancing fountain rising more than 100 feet...
The Lahore Development Authority (LDA) has completed the remodelling of the parking area in front of Lahore Railway Station along with the installation of a dancing fountain rising more than 100 feet, while work is also underway on another dancing fountain near Azadi Flyover on Circular Road.
LDA Director General Tahir Farooq visited several major development projects across Lahore, including Railway Station, Data Darbar and the Bhatti Chowk underpass, to review progress on ongoing works. LDA Chief Engineer Israr Saeed and TEPA Chief Engineer Iqrar Hussain briefed him on the status of the projects.
During his visit to Railway Station, the LDA chief inspected the colourful dancing fountain installed in the parking area. Officials said the fountain, installed on the directions of the Punjab chief minister, is the first of its kind in Lahore to rise more than 100 feet.
According to the LDA, a large number of people visited Railway Station on August 13 and 14 during Independence Day celebrations, where the dancing fountain, Independence Day-themed decorations and newly developed seating area attracted considerable public interest.
Tahir Farooq said the remodelling of the parking area in front of Railway Station had given the entire area a modern and refreshed appearance. He said a second dancing fountain was also being installed on Circular Road near Azadi Flyover.
He directed officials to complete the remaining finishing works around Railway Station at the earliest. Instructions were also issued to complete a designated sitting area for porters, install fans, provide drinking water and improve traffic signage to better guide visitors.
The LDA director general also inspected ongoing development works around Data Darbar. He was informed that escalators had been installed at the pedestrian underpass in front of the shrine to facilitate elderly citizens.
He directed officials to complete the remaining finishing works at the pedestrian underpass without delay.
During a briefing on the Bhatti Chowk underpass, officials said the main construction work had been completed and lane marking had also been carried out. Farooq directed the relevant teams to complete the remaining beautification work on the underpass structure.
He also reviewed work on a protected U-turn being developed on Circular Road and ordered that the remaining work be completed within the next few days.
The TEPA chief engineer assured the LDA director general that the remaining beautification, service road and protected U-turn works would be completed shortly.
Farooq also directed officials to establish a dedicated Gosha e Mazdoor sitting area for labourers on Circular Road at the earliest.
Officials from TEPA, LDA, NESPAK and the project contractor were also present during the visit.