Back to home

City and District Real Estate News

5 news articles

Rawalpindi Ring Road Phase II Feasibility Completed, Rs9 Billion Thallian/Hakla Expansion Emerges as Preferred Option

Rawalpindi Ring Road Phase II Feasibility Completed, Rs9 Billion Thallian/Hakla Expansion Emerges as Preferred Option

▫️NESPAK recommends widening the 15.3-kilometre M-2 motorway section from Thallian to Hakla from three to five lanes in each direction, making it the least-cost option among three proposed alignments

Rawalpindi : ReNews PakistanThe feasibility study for Phase-II of the Rawalpindi Ring Road has been completed, with NESPAK identifying the expansion of the existing M-2 motorway corridor between Thallian and Hakla Interchange as the most...

Rawalpindi : ReNews Pakistan
The feasibility study for Phase-II of the Rawalpindi Ring Road has been completed, with NESPAK identifying the expansion of the existing M-2 motorway corridor between Thallian and Hakla Interchange as the most feasible and least expensive of three proposed options.
Under the preferred alignment, the existing motorway section from Thallian to Hakla Interchange, which forms part of the China Pakistan Economic Corridor route, would be widened from three lanes to five lanes in each direction.
The proposed widening would cover approximately 15.3 kilometres and is estimated to cost around Rs 9 billion, significantly lower than the two alternative alignments examined during the feasibility process.
The second option proposes construction of an additional 19.5 kilometre route at an estimated cost of Rs18 billion, while the third option involves a 26.5 kilometre alignment on the western side of the motorway with a projected cost of around Rs 24 billion.
The assessment therefore places the first option at a clear cost advantage, while also allowing planners to use an existing major transport corridor instead of constructing an entirely new route.
The completion of the feasibility study represents an important step towards determining the future extension of the Rawalpindi Ring Road and improving connectivity between Thallian and Hakla. However, the preferred option will still require approval from the relevant authorities before implementation can begin.
Meanwhile, substantial progress has already been made on Phase-I of the project, which stretches approximately 38.3 kilometres from GT Road at Banth Mor to Thallian Interchange.
The main carriageway of Phase-I has largely been completed, while four of its five interchanges — Banth, Chakbeli Khan, Adiala and Chakri — have also been completed.
Work is continuing on the fifth interchange at Thallian after its design was expanded to provide broader connectivity. Despite the remaining work at the interchange, the Ring Road has already been connected with the motorway network.
Construction of toll plazas and installation of the tolling system are now among the major outstanding components of Phase-I.
Once the remaining toll-related infrastructure is completed, the project is expected to be transferred from the Project Management Unit to the Punjab Ring Road Authority, which will assume responsibility for its operation and management.
The Ring Road project has faced several revisions to its completion and inauguration schedule. August 14, 2026, had most recently been indicated as the expected inauguration date, but the opening did not take place because the tolling infrastructure had not yet been completed.
A service area established along the Ring Road, which had previously attracted controversy, has also been removed from the project route.
The proposed Phase-II extension is considered important for strengthening regional road connectivity by providing a more efficient link between the completed Ring Road corridor and the Hakla Interchange on the motorway network.
If the Rs 9 billion widening option receives final approval, the project would add two lanes in each direction along the 15.3 kilometre Thallian/Hakla section, potentially increasing traffic capacity while avoiding the substantially higher costs associated with constructing the two alternative routes.
The final alignment, funding mechanism and implementation schedule will depend on subsequent government approvals and decisions by the relevant project authorities.
Rawalpindi Launches Murree Road Repairs and Beautification Work Under Rs4 Billion Development Programme

Rawalpindi Launches Murree Road Repairs and Beautification Work Under Rs4 Billion Development Programme

▫️ Road rehabilitation begins from Faizabad to Liaquat Bagh, including repairs to 6th Road and Chandni Chowk flyovers

The Punjab Highway Department has initiated repair and rehabilitation work on Murree Road between Faizabad and Liaquat Bagh, including damaged sections of the 6th Road and Chandni Chowk flyovers.

SBCA Receives 17 Bids for Gul Plaza Demolition Project in Karachi

SBCA Receives 17 Bids for Gul Plaza Demolition Project in Karachi

▫️ Sindh Building Control Authority begins technical evaluation of contractors, with financial bids scheduled to open on November 24

Karachi | ReNews Sindh CorrespondentThe Sindh Building Control Authority (SBCA) has initiated the contractor selection process for the demolition of Gul Plaza in Karachi, receiving technical bids from 17 interested companies. The bids we...

Punjab Cabinet Committee Approves 13 Legislative and Privatisation Agenda Items, Focuses on Investment and Land Reforms

Punjab Cabinet Committee Approves 13 Legislative and Privatisation Agenda Items, Focuses on Investment and Land Reforms

▫️ Punjab government prioritises industrial infrastructure, modernisation of land records, investment promotion and faster implementation of development projects

The Punjab Cabinet Standing Committee on Legislative Affairs and Privatisation has approved all 13 agenda items during its 42nd meeting, chaired by Provincial Finance and Parliamentary Affairs Minister Mujtaba Shuja-ur-Rehman at the Civi...

Karachi Court Dismisses Property Ownership Suit, SHC Reserves Verdict in 53-Acre Land Dispute

Karachi Court Dismisses Property Ownership Suit, SHC Reserves Verdict in 53-Acre Land Dispute

▫️ Civil court rejects Wado Akharo Trust’s claim against federal government and Evacuee Trust Property Board over disputed property ownership

Karachi | ReNews Sindh CorrespondentA senior civil judge in Karachi South has dismissed a civil suit filed by Wado Akharo Trust against the federal government and others, declaring it not maintainable. The trust argued that the disputed ...

CDA Completes Over 68% Development Work in Islamabad’s Sector E-12, Continues Handover of Residential Plots

CDA Completes Over 68% Development Work in Islamabad’s Sector E-12, Continues Handover of Residential Plots

▫️ CDA retrieves 1,135 kanals of encroached land; Chairman Sohail Ashraf directs speedy completion of remaining development work.

The Capital Development Authority (CDA) has completed more than 68% of development work in Islamabad’s Sector E-12, where infrastructure development has remained delayed for nearly four decades.

More City and District Real Estate News

More Real Estate News

National Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →