Sindh Cabinet Approves Revised Rs 14.24 Billion DHA Karachi Water Pipeline Project Amid Cost Escalation
سندھ کابینہ نے لاگت میں اضافے کے بعد ڈی ایچ اے کراچی واٹر پائپ لائن منصوبے کیلئے 14.24 ارب روپے کی منظوری دیدی
▫️Project cost rises by nearly 40% due to engineering redesign, upgraded infrastructure, inflation, and higher taxes
Karachi : ReNews PakistanThe Sindh Cabinet has approved a revised budget of Rs 14.237 billion for the construction of a dedicated water supply pipeline that will deliver water from Dumlottee, on the outskirts of Karachi, to the Defence H...
The Sindh Cabinet has approved a revised budget of Rs 14.237 billion for the construction of a dedicated water supply pipeline that will deliver water from Dumlottee, on the outskirts of Karachi, to the Defence Housing Authority (DHA). The decision reflects a nearly 40 percent increase over the project's original estimated cost of Rs10.56 billion, which was approved in July 2025 to address the long standing water shortage affecting DHA residents.
The project is intended to provide a reliable and sustainable water supply to one of Karachi’s largest residential communities, where many households have depended heavily on private water tankers due to inadequate municipal water availability.
According to the Sindh government, the revised Engineering, Procurement and Construction (EPC) cost has increased following significant changes to the project's technical design and scope. The Frontier Works Organisation (FWO) has been entrusted with executing the pipeline project.
Senior Minister Sharjeel Inam Memon stated that the revised estimate incorporates engineering modifications, upgraded pipeline materials, inflationary pressures, higher taxation, and the inclusion of additional infrastructure such as modern filtration facilities, a real time monitoring system, and other operational improvements designed to enhance the project's long term efficiency and reliability.
In addition to approving the revised construction cost, the cabinet authorised the appointment of a project consultant in accordance with the applicable public procurement laws to oversee implementation and ensure compliance with technical and regulatory standards.
The cabinet also approved an increase in the bulk water tariff from Rs 0.60 per gallon to Rs 0.70 per gallon as part of the project's updated financial framework. Officials said the revised tariff structure is intended to support the project's operational sustainability while maintaining long term financial viability.
Despite the higher upfront investment, the updated financial model indicates that the dedicated water supply system is expected to generate net savings of approximately Rs 2.31 billion over the next 10 years by reducing dependence on costly water tanker services, improving distribution efficiency, and lowering operational losses.
The project forms part of Sindh's broader efforts to strengthen Karachi's urban water infrastructure and improve access to dependable water supplies for rapidly growing residential areas through modern engineering solutions and long term investment in essential public utilities.