Sindh Cabinet Approves Revised Rs 14.24 Billion DHA Karachi Water Pipeline Project Amid Cost Escalation

Sindh Cabinet Approves Revised Rs 14.24 Billion DHA Karachi Water Pipeline Project Amid Cost Escalation

▫️Project cost rises by nearly 40% due to engineering redesign, upgraded infrastructure, inflation, and higher taxes

Karachi : ReNews PakistanThe Sindh Cabinet has approved a revised budget of Rs 14.237 billion for the construction of a dedicated water supply pipeline that will deliver water from Dumlottee, on the outskirts of Karachi, to the Defence H...

Karachi : ReNews Pakistan
The Sindh Cabinet has approved a revised budget of Rs 14.237 billion for the construction of a dedicated water supply pipeline that will deliver water from Dumlottee, on the outskirts of Karachi, to the Defence Housing Authority (DHA). The decision reflects a nearly 40 percent increase over the project's original estimated cost of Rs10.56 billion, which was approved in July 2025 to address the long standing water shortage affecting DHA residents.
The project is intended to provide a reliable and sustainable water supply to one of Karachi’s largest residential communities, where many households have depended heavily on private water tankers due to inadequate municipal water availability.
According to the Sindh government, the revised Engineering, Procurement and Construction (EPC) cost has increased following significant changes to the project's technical design and scope. The Frontier Works Organisation (FWO) has been entrusted with executing the pipeline project.
Senior Minister Sharjeel Inam Memon stated that the revised estimate incorporates engineering modifications, upgraded pipeline materials, inflationary pressures, higher taxation, and the inclusion of additional infrastructure such as modern filtration facilities, a real time monitoring system, and other operational improvements designed to enhance the project's long term efficiency and reliability.
In addition to approving the revised construction cost, the cabinet authorised the appointment of a project consultant in accordance with the applicable public procurement laws to oversee implementation and ensure compliance with technical and regulatory standards.
The cabinet also approved an increase in the bulk water tariff from Rs 0.60 per gallon to Rs 0.70 per gallon as part of the project's updated financial framework. Officials said the revised tariff structure is intended to support the project's operational sustainability while maintaining long term financial viability.
Despite the higher upfront investment, the updated financial model indicates that the dedicated water supply system is expected to generate net savings of approximately Rs 2.31 billion over the next 10 years by reducing dependence on costly water tanker services, improving distribution efficiency, and lowering operational losses.
The project forms part of Sindh's broader efforts to strengthen Karachi's urban water infrastructure and improve access to dependable water supplies for rapidly growing residential areas through modern engineering solutions and long term investment in essential public utilities.
Federal Minister Orders Early Completion of Lowari Tunnel and Chitral Highway Projects

Federal Minister Orders Early Completion of Lowari Tunnel and Chitral Highway Projects

▫️ Completion of road projects aimed at improving regional connectivity, supporting tourism and facilitating local communities

Federal Minister for Communications Abdul Aleem Khan has directed the authorities concerned to accelerate the remaining construction and development works on the Lowari Tunnel and Chitral Highway projects.

LDA to Auction Commercial Plots in Lahore Technology Park on December 3

LDA to Auction Commercial Plots in Lahore Technology Park on December 3

▫️ Balloting for Pine Axis and Pine Executive plots scheduled for December 10 as LDA expands investment opportunities

The Lahore Development Authority (LDA) has announced that commercial plots in Lahore Technology Park, located on Ferozepur Road near Arfa Karim Software and Technology Tower, will be auctioned on December 3, 2026, at Expo Centre, Johar T...

KP Plans Independent Commission to Resolve Land Ownership Dispute Between Kolai-Palas and Battagram Tribes

KP Plans Independent Commission to Resolve Land Ownership Dispute Between Kolai-Palas and Battagram Tribes

▫️ Hazara administration to seek provincial approval for an impartial settlement commission to determine disputed land ownership

The Hazara divisional administration has decided to approach the Khyber Pakhtunkhwa government for the establishment of an independent settlement commission to resolve a longstanding land ownership dispute between rival tribes in Kolai-P...

FGEHA Approves Relocation of Three Islamabad Plots to Preserve 300-Year-Old Trees

FGEHA Approves Relocation of Three Islamabad Plots to Preserve 300-Year-Old Trees

▫️ Three one-kanal residential plots in Sector G-14/3 to be shifted as authority plans a park around two historic banyan trees

The Federal Government Employees Housing Authority (FGEHA) has approved in principle the relocation of three residential plots in Islamabad's Sector G-14/3 to protect two banyan trees estimated to be around 300 years old.

Pakistan Railways Issues Eviction Notices to 147 Property Owners in Hyderabad Over Land Ownership Dispute

Pakistan Railways Issues Eviction Notices to 147 Property Owners in Hyderabad Over Land Ownership Dispute

▫️ Railways claims more than 1,152 acres across Hyderabad district as property owners question eviction notices and demand legal protection

Pakistan Railways has issued approximately 147 eviction notices to owners and occupants of residential and commercial properties in Hyderabad, alleging unauthorised occupation of railway land.

Punjab Signs Agreements for Modern Toll Plazas on 318 Kilometres of Major Roads

Punjab Signs Agreements for Modern Toll Plazas on 318 Kilometres of Major Roads

▫️ Ten toll plazas to be developed across Muridke–Narowal–Shakargarh Road, Faisalabad–Samundri–Rajana Road and Faisalabad Ring Road

The Punjab government has signed agreements with private companies to develop and operate ten modern toll plazas across 318 kilometres of major road networks.

FDA Begins Construction of New Canal Road Bridge to Ease Traffic Congestion in Faisalabad

FDA Begins Construction of New Canal Road Bridge to Ease Traffic Congestion in Faisalabad

▫️ New 100 by 85 foot bridge near Pipanwala Bridge to provide a dedicated U-turn and improve traffic movement

The Faisalabad Development Authority (FDA) has initiated construction work on a Canal Road remodelling project aimed at reducing traffic congestion near Treat Bakery.

Islamabad High Court Directs CDA to Decide Saidpur Village Residents' Petitions Within 30 Days

Islamabad High Court Directs CDA to Decide Saidpur Village Residents' Petitions Within 30 Days

▫️ Court stresses protection of ancestral homes and residents' right to compensation, ruling out forced evictions

The Islamabad High Court has directed the Capital Development Authority (CDA) Board to decide petitions filed by Saidpur Village residents within 30 days, in accordance with the law and a recent Federal Constitutional Court judgment.

Hyderabad Development Authority's Auction of 991 Plots Faces Legal Objections Over Land Ownership

Hyderabad Development Authority's Auction of 991 Plots Faces Legal Objections Over Land Ownership

▫️ High value residential plots in Latifabad and Qasimabad under scrutiny as HDA is asked to establish its legal authority to sell

Hyderabad | ReNews Sindh CorrespondentThe Hyderabad Development Authority (HDA) is facing legal objections over its proposed auction of 991 residential plots in Latifabad and Qasimabad, potentially worth billions of rupees.

More City and District Real Estate News

More Real Estate News

National Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →