Defence Ministry Warns of Protests Over Delayed Mangla Dam Compensation Payments

Defence Ministry Warns of Protests Over Delayed Mangla Dam Compensation Payments

▫️Only 46 out of 449 compensation cases have received partial payments, while Rs4.4 billion remains pending with the Ministry of Finance

Islamabad | ReNews Pakistan The Ministry of Defence has warned the Prime Minister’s Office and the Ministry of Finance that continued delays in clearing compensation claims of families affected by the Mangla Dam Raising Project could ...

Islamabad | ReNews Pakistan
The Ministry of Defence has warned the Prime Minister’s Office and the Ministry of Finance that continued delays in clearing compensation claims of families affected by the Mangla Dam Raising Project could trigger public protests and create internal security concerns in the area.
According to well-informed sources, the Ministry of Defence has raised the issue of pending compensation payments related to the Mangla Dam Raising Project, which was carried out between June 2004 and September 2007. The project was launched to restore the dam’s water storage capacity, which had been reduced over the years due to sedimentation.
The ministry noted that the project led to the inundation of around 15,780 acres, or 64 square kilometres, of land in Mirpur district of Azad Jammu and Kashmir. As a result, residents of 118 villages were displaced and became entitled to compensation and resettlement support.
In June 2003, a compensation package worth Rs26 billion was agreed between WAPDA and the Azad Jammu and Kashmir government. The package covered land acquisition, housing compensation and resettlement of the affected population.
However, sources said a large number of affected families are still waiting for their payments. Out of 449 compensation cases, only 46 individuals have so far received partial compensation. The disbursement of Rs4.4 billion remains pending with the Ministry of Finance.
The Ministry of Defence cautioned that the delay is increasing resentment among the affected people and could lead to legal challenges as well as public demonstrations. The ministry warned that such protests may have an impact on the internal security situation in the region.
In its communication, the ministry urged Special Secretary to the Prime Minister Shakeel Ahmed Mangnejo and Finance Secretary ImdadUllah Bosal to expedite the release of pending funds. It said the matter should be resolved urgently to address the concerns of displaced families and prevent further escalation.
The issue has also been discussed during negotiations between representatives of the Azad Jammu and Kashmir Action Committee and the federal and AJ&K governments.
For the resettlement of displaced families, a new city near Mirpur was developed, along with four small towns around the reservoir. These settlements were planned to accommodate the people affected by the expansion of the dam.
The matter had also reached the Supreme Court of Pakistan. In August 2011, the court disposed of a petition filed by the victims seeking compensation, ruling that the issue fell outside its jurisdiction. The petitioners were directed to approach the Supreme Court of Azad Jammu and Kashmir.
At the time, WAPDA informed the court that it had already transferred more than Rs50 billion to the AJ&K government for compensation. WAPDA had also awarded a Rs164 million contract to consulting firms for a feasibility study to upgrade the 1,000MW Mangla Power Station.
The Mangla Power House currently generates up to 1,150MW during high reservoir levels, exceeding its rated capacity of 1,000MW due to permissible overloading of 15 percent.
KP Development Council to Review Rs 160 Billion Development Programme Across 12 Districts

KP Development Council to Review Rs 160 Billion Development Programme Across 12 Districts

▫️ ARDC meeting in Peshawar to assess infrastructure projects, public services and progress on 100 development targets

The Area Representative and Development Council (ARDC) is scheduled to meet in Peshawar on November 26 to review development projects, security arrangements and administrative measures across 12 designated districts of Khyber Pakhtunkhwa.

FGEHA Announces Red Notices for Housing Scheme Allottees Over Outstanding Payments

FGEHA Announces Red Notices for Housing Scheme Allottees Over Outstanding Payments

▫️ Authority strengthens recovery procedures to collect unpaid instalments and other financial dues across housing projects

The Federal Government Employees Housing Authority (FGEHA) has decided to issue red notices to housing scheme allottees who have failed to make payments against their allotted properties.

More Real Estate News

City and District Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →