Published: May 23, 2026 - 5:15 PM
Hyderabad Sukkur Motorway Northern Sections Expected to Be Completed by May 2029
حیدرآباد سکھر موٹروے کے شمالی سیکشنز مئی 2029 تک مکمل ہونے کا امکان
▫️Islamic Development Bank and OPEC Fund are financing key sections, while southern portions will be developed under public private partnership
Islamabad | ReNews Pakistan The government has accelerated work on the long delayed Hyderabad Sukkur Motorway, with three northern sections of the M 6 project expected to be completed between March and May 2029.
The government has accelerated work on the long delayed Hyderabad Sukkur Motorway, with three northern sections of the M 6 project expected to be completed between March and May 2029.
According to official documents, progress is underway on Sections III, IV and V, which cover the Nawabshah to Sukkur stretch of the motorway.
Sections IV and V, covering Naushero Feroz to Ranipur and Ranipur to Sukkur, are being financed by the Islamic Development Bank. The prequalification notice for these sections was issued on December 13, 2025, while the evaluation report was submitted to the lender on March 18, 2026. Civil works contracts are expected to be awarded between September and October 2026.
The Islamic Development Bank approved $475 million in financing for the two sections on September 29, 2025, while the financing agreement was signed on January 19, 2026.
Section III, from Nawabshah to Naushero Feroz, is being financed by the OPEC Fund, which approved $230 million for the section on March 25, 2026. Authorities expect the bidding process to move forward soon, with the contract award targeted for October 2026.
Meanwhile, Sections I and II, covering Hyderabad to Tando Adam and Tando Adam to Nawabshah, will be developed under a public private partnership model already cleared by ECNEC. The Asian Development Bank has been engaged as transaction adviser, with its study expected to be completed within four months. The concession award for these southern sections is anticipated by February 2027.