Karachi Infrastructure Push Intensifies as Sindh CM Sets Deadlines for Key Projects
کراچی کے بڑے ترقیاتی منصوبوں میں تیزی، وزیراعلیٰ سندھ نے اہم پراجیکٹس کیلئے ڈیڈ لائن مقرر کر دی
▫️Bhutto Expressway to open before eid; Red Line mixed traffic lanes to be completed within two months
Karachi | ReNews Pakistan Sindh Chief Minister Murad Ali Shah has accelerated the pace of major infrastructure development across Karachi, setting firm deadlines for the completion of critical transport projects, including the Karachi...
Sindh Chief Minister Murad Ali Shah has accelerated the pace of major infrastructure development across Karachi, setting firm deadlines for the completion of critical transport projects, including the Karachi BRT Red Line and Shahrah e Bhutto corridor.
During early morning visits to several ongoing project sites, the chief minister reviewed progress and directed authorities to ensure both speed and quality in execution. He made it clear that delays or substandard work would not be tolerated, emphasising the government’s commitment to improving urban mobility.
“Our priority is to restore smooth traffic flow and provide safe, reliable infrastructure to the people of Karachi,” Shah said, adding that both the Red Line and Shahrah e Bhutto are vital for the city’s transport network.
He announced that the Bhutto Expressway would be opened to traffic before Eid, describing it as a significant relief measure for commuters. Additionally, he instructed that all mixed-traffic lanes along the Red Line corridor be completed within two months.
Officials, including Transport Secretary Asad Zamin and TransKarachi CEO Zubair Channa, briefed the chief minister on ongoing work. They confirmed that repair, patchwork, and rehabilitation of mixed traffic lanes are underway, alongside road widening through adjustments to New Jersey barriers.
Expressing concern over recurring waterlogging issues, Shah directed authorities to develop a permanent solution and ordered that construction activities be carried out in multiple shifts to ensure timely completion while minimising inconvenience to the public.
On the Shahrah e Bhutto project, officials reported that approximately 93 percent of the 38 a kilometre stretch, from Jam Sadiq Interchange to M-9 Kathore Interchange, has been completed, with the remaining work expected to conclude within weeks.
The chief minister also ordered the immediate resumption of work on the Mosamiyat Flyover, assuring full provision of funds and resources. He noted that the project is crucial for easing congestion along University Road.
Further, Shah reviewed progress on the Munawar Chowrangi Underpass, being constructed to facilitate traffic flow from Kamran Chowrangi towards Gulistan e Jauhar, and directed officials to expedite its completion.
Separately, he inspected the Azeempura Flyover in Shah Faisal Colony and instructed that it be completed within 90 days. The project aims to ensure signal-free movement towards Jinnah Terminal and adjoining areas.
Karachi Mayor Murtaza Wahab also briefed the chief minister on the Pehlwan Goth Road project, which includes the construction of a dual carriageway, improved drainage and sewerage systems, and installation of LED street lighting.
The renewed push reflects the Sindh government’s broader effort to address Karachi’s long-standing traffic challenges and modernise its urban infrastructure.