Neelum Jhelum Hydropower Project Suffers Rs 128 Billion Losses as Audit Exposes Operational and Financial Crisis

Neelum Jhelum Hydropower Project Suffers Rs 128 Billion Losses as Audit Exposes Operational and Financial Crisis

▫️Audit reveals Rs 267 billion in uninsured assets, missed power generation targets and growing liabilities that threaten the long term viability of the 969 megawatt hydropower project

Islamabad | ReNews PakistanPakistan's flagship Neelum Jhelum Hydropower Project has suffered financial losses exceeding Rs 128 billion during the fiscal year 2024 25, according to the latest audit conducted by the Auditor General of Paki...

Islamabad | ReNews Pakistan
Pakistan's flagship Neelum Jhelum Hydropower Project has suffered financial losses exceeding Rs 128 billion during the fiscal year 2024 25, according to the latest audit conducted by the Auditor General of Pakistan. The report paints a troubling picture of persistent operational failures, prolonged plant shutdowns, tunnel collapses, rising debt obligations and weak financial management that have significantly undermined the project's long term sustainability.
The audit states that the 969 megawatt hydropower project recorded a net loss of Rs 29.41 billion during the fiscal year, while business interruption losses reached Rs 99.18 billion following extended shutdowns caused by the collapse of the tailrace tunnel in 2022 and the headrace tunnel in May 2024. These disruptions kept the powerhouse out of operation for extended periods, resulting in substantial revenue losses.
According to the report, investigations into both tunnel collapses remain incomplete. Auditors found that project management failed to adequately address technical defects, renew essential insurance coverage or obtain compensation for losses resulting from the structural failures. During the review period, project assets worth approximately Rs 267 billion remained uninsured, exposing the project to significant financial risk.
The audit also highlighted the project's continued inability to achieve its planned electricity generation targets. Since its commissioning, the Neelum Jhelum Hydropower Project has never met its annual generation target of 5,150 gigawatt hours, including years when the plant was fully operational. The report attributes this underperformance to operational inefficiencies and recurring technical challenges.
Another major concern identified in the audit is the absence of an approved reference tariff from the National Electric Power Regulatory Authority, which resulted in an estimated Rs 77.35 billion regulatory revenue shortfall. The delayed tariff approval has further weakened the project's financial position and limited its ability to recover operational costs.
Financial indicators presented in the audit reveal a rapidly deteriorating balance sheet. As of June 30, 2025, the project's current liabilities exceeded its current assets by Rs 307.89 billion, largely due to debt repayment defaults and the reclassification of long term loans as current liabilities.
The report further notes that the project has fallen well short of recovering its original investment. Against an approved project cost of Rs 418.89 billion, only Rs 180.17 billion had been recovered by the end of FY2024 25. In addition, nearly 69 percent of receivables remained overdue for more than 120 days, reflecting serious weaknesses in cash flow management and revenue collection.
The Auditor General concluded that persistent underperformance in electricity generation, prolonged operational outages, delayed regulatory approvals, increasing debt burdens and inadequate risk management practices have prevented the Neelum Jhelum Hydropower Project from achieving its intended financial and operational objectives. The report calls attention to the urgent need for corrective measures to improve governance, strengthen technical oversight and restore the project's long term financial viability.
Sindh Govt Approves 16.5-Kilometre Four-Lane Karachi Port Expressway

Sindh Govt Approves 16.5-Kilometre Four-Lane Karachi Port Expressway

▫️ Public-private partnership project will connect Shahrah-e-Bhutto with Karachi Port’s East Wharf; contract includes 2.5 years of construction and 25 years of operation

Sindh Chief Minister Syed Murad Ali Shah has approved the Karachi Port to Qayyumabad corridor, a 16.

Punjab Cabinet Approves Rs 3.7965 Billion in Funds for WASA on Housing Secretary’s Recommendation

Punjab Cabinet Approves Rs 3.7965 Billion in Funds for WASA on Housing Secretary’s Recommendation

▫️WASA Phase III to include purchase of high-pressure jetting, suction and desilting machinery; Pumps and mechanical equipment also included to improve drainage and water supply

The Punjab Cabinet has approved Rs 3.

Margalla Avenue Extension to Connect Islamabad with M-1 Motorway, CDA Says

Margalla Avenue Extension to Connect Islamabad with M-1 Motorway, CDA Says

▫️ 35% of the project is complete, with work continuing around the clock on the Islamabad section

Construction of the Margalla Avenue extension, planned to connect N-5 with the M-1 Motorway, is progressing, with 35% of the project completed, the Capital Development Authority (CDA) said on November 9.

CDA to Seal Offices of 40 Illegal Housing Societies in Islamabad

CDA to Seal Offices of 40 Illegal Housing Societies in Islamabad

▫️ Operation expected within a week, Planning Wing seeks support from ICT administration and Islamabad Police; investors question approvals and stalled development

The Capital Development Authority (CDA) is preparing to seal the offices of 40 housing societies it has identified as illegal, with the operation expected to begin within the next week.

Tarbela 5th Extension Work Halted After Rock Collapse; Land Framework Covers Transmission Line

Tarbela 5th Extension Work Halted After Rock Collapse; Land Framework Covers Transmission Line

▫️ Water entered active tunnel and powerhouse work areas during excavation; WAPDA says the main structures remain undamaged

Construction work on the Tarbela 5th Extension Hydropower Project was suspended after a rock mass collapsed during excavation on Monday, allowing water from the dam’s intake pit to surge into a connecting tunnel and the under-constructio...

Punjab Govt Launches 120-Kanal Blind Dolphin Resort on Site Targeted for Acquisition in 2020

Punjab Govt Launches 120-Kanal Blind Dolphin Resort on Site Targeted for Acquisition in 2020

▫️ The riverside facility at Taunsa Barrage combines tourism amenities with a stated commitment to wildlife conservation

Punjab Chief Minister Maryam Nawaz Sharif has announced the launch of the Tourism Development Corporation of Punjab (TDCP) Blind Dolphin Resort at Taunsa Barrage in Kot Addu.

More Real Estate News

City and District Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →