Tarbela 5th Extension Work Halted After Rock Collapse; Land Framework Covers Transmission Line
چٹانیں کھسکنے سے تربیلا ففتھ ایکسٹینشن کا کام معطل، پانی سرنگ اور پاور ہاؤس میں داخل؛ ٹرانسمیشن لائن کیلئے اراضی فریم ورک بھی منصوبے میں شامل
▫️ Water entered active tunnel and powerhouse work areas during excavation; WAPDA says the main structures remain undamaged
Construction work on the Tarbela 5th Extension Hydropower Project was suspended after a rock mass collapsed during excavation on Monday, allowing water from the dam’s intake pit to surge into a connecting tunnel and the under-constructio...
WAPDA said the incident occurred during excavation of the second bench of the connecting tunnel. Workers were evacuated, the intake pit was drained and dewatering began at the powerhouse. Haripur Deputy Commissioner Waseem Ahmed said one worker was swept away by the water but rescued. No deaths were reported. WAPDA said the main Tunnel 5, powerhouse, tailrace culvert, and switchyard had not been damaged; project officials, the engineer, and the contractor were assessing the site.
District administration reports described the construction suspension as indefinite. WAPDA’s statement said teams were assessing the situation but did not give a date for work to resume. The authority also rejected reports that the main tunnel had collapsed, saying the water entered work areas after the rock failure during excavation. The project is being built around Tarbela Dam’s existing Tunnel 5, originally constructed for irrigation releases. Its scope includes converting the tunnel for hydropower, building a powerhouse and installing three generating units. Once complete, the extension is intended to add 1,530 megawatts to Tarbela’s installed generation capacity.
Land issues form a separate part of the wider project. The Asian Infrastructure Investment Bank says the project includes a transmission line and that WAPDA and the National Grid Company prepared a land acquisition and resettlement framework, including plans for the transmission route and a new grid station. The framework relates to the project’s power evacuation infrastructure; available reports have not linked land acquisition to Monday’s rock collapse. The latest incident follows an earlier construction setback: the downstream cofferdam collapsed in August 2025. A government inquiry reported in July held WAPDA, the contractor and the consultant responsible, citing post-contract design changes among the causes. The media reported that the earlier collapse contributed to the project’s cost rising from Rs 82 billion to Rs 317 billion and pushed the completion target to the end of June 2028. The latest rock collapse is a separate incident; its cause and effect on the schedule remain under assessment.