Tarbela 5th Extension Work Halted After Rock Collapse; Land Framework Covers Transmission Line

Tarbela 5th Extension Work Halted After Rock Collapse; Land Framework Covers Transmission Line

▫️ Water entered active tunnel and powerhouse work areas during excavation; WAPDA says the main structures remain undamaged

Construction work on the Tarbela 5th Extension Hydropower Project was suspended after a rock mass collapsed during excavation on Monday, allowing water from the dam’s intake pit to surge into a connecting tunnel and the under-constructio...

Construction work on the Tarbela 5th Extension Hydropower Project was suspended after a rock mass collapsed during excavation on Monday, allowing water from the dam’s intake pit to surge into a connecting tunnel and the under-construction powerhouse.

WAPDA said the incident occurred during excavation of the second bench of the connecting tunnel. Workers were evacuated, the intake pit was drained and dewatering began at the powerhouse. Haripur Deputy Commissioner Waseem Ahmed said one worker was swept away by the water but rescued. No deaths were reported. WAPDA said the main Tunnel 5, powerhouse, tailrace culvert, and switchyard had not been damaged; project officials, the engineer, and the contractor were assessing the site.

District administration reports described the construction suspension as indefinite. WAPDA’s statement said teams were assessing the situation but did not give a date for work to resume. The authority also rejected reports that the main tunnel had collapsed, saying the water entered work areas after the rock failure during excavation. The project is being built around Tarbela Dam’s existing Tunnel 5, originally constructed for irrigation releases. Its scope includes converting the tunnel for hydropower, building a powerhouse and installing three generating units. Once complete, the extension is intended to add 1,530 megawatts to Tarbela’s installed generation capacity.

Land issues form a separate part of the wider project. The Asian Infrastructure Investment Bank says the project includes a transmission line and that WAPDA and the National Grid Company prepared a land acquisition and resettlement framework, including plans for the transmission route and a new grid station. The framework relates to the project’s power evacuation infrastructure; available reports have not linked land acquisition to Monday’s rock collapse. The latest incident follows an earlier construction setback: the downstream cofferdam collapsed in August 2025. A government inquiry reported in July held WAPDA, the contractor and the consultant responsible, citing post-contract design changes among the causes. The media reported that the earlier collapse contributed to the project’s cost rising from Rs 82 billion to Rs 317 billion and pushed the completion target to the end of June 2028. The latest rock collapse is a separate incident; its cause and effect on the schedule remain under assessment.
KP Proposes Rs160.18 Billion Development Package for Roads, Infrastructure and Public Facilities

KP Proposes Rs160.18 Billion Development Package for Roads, Infrastructure and Public Facilities

▫️ Road expansion, new schools, healthcare facilities and infrastructure improvements among key priorities

Peshawar | ReNews KP CorrespondentThe Khyber Pakhtunkhwa government has proposed a Rs160.18 billion development package aimed at improving road infrastructure, public facilities, education, healthcare and security across 37 districts. Un...

World Bank Upgrades Punjab Land Records Digitisation Project Rating to Highly Satisfactory

World Bank Upgrades Punjab Land Records Digitisation Project Rating to Highly Satisfactory

▫️ Punjab exceeds major land reform targets, with 69.92 million land rights registered and digital cadastral maps covering 86% of the province

The World Bank has upgraded the Punjab Urban Land Systems Enhancement Project's development and implementation ratings from Satisfactory to Highly Satisfactory after several key targets were exceeded.

Pakistan Pushes Regional Transport Infrastructure Development to Strengthen Trade Connectivity

Pakistan Pushes Regional Transport Infrastructure Development to Strengthen Trade Connectivity

▫️ Federal Minister Abdul Aleem Khan highlights CPEC road projects, M-6 Motorway financing and cross border railway links at UN ESCAP conference in Bangkok

Federal Minister for Communications Abdul Aleem Khan has called for stronger regional transport infrastructure and alternative trade corridors to improve connectivity between Central Asia, South Asia, China and the Middle East.

Government Approves 25-Year Public-Private Partnership for Two Sections of Sukkur Hyderabad M 6 Motorway

Government Approves 25-Year Public-Private Partnership for Two Sections of Sukkur Hyderabad M 6 Motorway

▫️Public Private Partnership Authority (P3A) Board approves separate concession agreements for 121 kilometres of motorway, allowing private investors to finance, construct and operate both sections

The Public Private Partnership Authority (P3A) Board has approved separate concession agreements for the development of Sections I and II of the Sukkur Hyderabad M 6 Motorway, covering a combined distance of 121 kilometres.

Federal Constitutional Court Dismisses LDA Appeal in 14 Marla Gulberg III Property Dispute

Federal Constitutional Court Dismisses LDA Appeal in 14 Marla Gulberg III Property Dispute

▫️ Court directs LDA to avoid wasting public funds on unnecessary litigation after repeated legal challenges over disputed land

Islamabad | ReNews National CorrespondentThe Federal Constitutional Court (FCC) has dismissed an appeal filed by the Lahore Development Authority (LDA) concerning a 14 marla property in Lahore’s Gulberg III area.

CDA Completes Over 96% Construction Work on 11-Storey National Police Academy in Islamabad

CDA Completes Over 96% Construction Work on 11-Storey National Police Academy in Islamabad

▫️ Modern training facility features 126 rooms, jogging track, rappelling towers and obstacle courses; major construction completed within 15 months

The Capital Development Authority (CDA) has completed more than 96% of construction work on the 11-storey National Police Academy building in Islamabad's Sector H 11.

CDA Issues Show Cause Notice to Jinnah Garden Phase II Over Illegal Development Along Soan River

CDA Issues Show Cause Notice to Jinnah Garden Phase II Over Illegal Development Along Soan River

▫️ Housing scheme accused of carrying out development without CDA approval and constructing a 1,200 foot wall, partly outside its approved boundaries.

The Capital Development Authority (CDA) has issued a show cause notice to Jinnah Garden Phase II on Kahuta Road in Islamabad’s Zone 5 over alleged unauthorised development and construction along the Soan River.

State Bank Issues New Financing Guidelines for REITs, Builders and Developers

State Bank Issues New Financing Guidelines for REITs, Builders and Developers

▫️ New regulations introduce property valuation requirements, construction monitoring and mandatory insurance or Takaful coverage for development projects

The State Bank of Pakistan (SBP) has introduced new financing guidelines for Real Estate Investment Trusts (REITs), builders and property developers to improve access to financing while strengthening risk management.

World Toilet Day Highlights Pakistan’s Sanitation Crisis as Millions Lack Safe Facilities

World Toilet Day Highlights Pakistan’s Sanitation Crisis as Millions Lack Safe Facilities

▫️ Over 58% of rural Pakistan lacks safely managed sanitation services, while 25 million people still practise open defecation

Pakistan joins the international community in observing World Toilet Day on November 19, drawing attention to the continuing shortage of safe sanitation facilities.

Tarbela 5th Extension Work Halted After Rock Collapse; Land Framework Covers Transmission Line

Tarbela 5th Extension Work Halted After Rock Collapse; Land Framework Covers Transmission Line

▫️ Water entered active tunnel and powerhouse work areas during excavation; WAPDA says the main structures remain undamaged

Construction work on the Tarbela 5th Extension Hydropower Project was suspended after a rock mass collapsed during excavation on Monday, allowing water from the dam’s intake pit to surge into a connecting tunnel and the under-constructio...

Construction work on the Tarbela 5th Extension Hydropower Project was suspended after a rock mass collapsed during excavation on Monday, allowing water from the dam’s intake pit to surge into a connecting tunnel and the under-construction powerhouse.

WAPDA said the incident occurred during excavation of the second bench of the connecting tunnel. Workers were evacuated, the intake pit was drained and dewatering began at the powerhouse. Haripur Deputy Commissioner Waseem Ahmed said one worker was swept away by the water but rescued. No deaths were reported. WAPDA said the main Tunnel 5, powerhouse, tailrace culvert, and switchyard had not been damaged; project officials, the engineer, and the contractor were assessing the site.

District administration reports described the construction suspension as indefinite. WAPDA’s statement said teams were assessing the situation but did not give a date for work to resume. The authority also rejected reports that the main tunnel had collapsed, saying the water entered work areas after the rock failure during excavation. The project is being built around Tarbela Dam’s existing Tunnel 5, originally constructed for irrigation releases. Its scope includes converting the tunnel for hydropower, building a powerhouse and installing three generating units. Once complete, the extension is intended to add 1,530 megawatts to Tarbela’s installed generation capacity.

Land issues form a separate part of the wider project. The Asian Infrastructure Investment Bank says the project includes a transmission line and that WAPDA and the National Grid Company prepared a land acquisition and resettlement framework, including plans for the transmission route and a new grid station. The framework relates to the project’s power evacuation infrastructure; available reports have not linked land acquisition to Monday’s rock collapse. The latest incident follows an earlier construction setback: the downstream cofferdam collapsed in August 2025. A government inquiry reported in July held WAPDA, the contractor and the consultant responsible, citing post-contract design changes among the causes. The media reported that the earlier collapse contributed to the project’s cost rising from Rs 82 billion to Rs 317 billion and pushed the completion target to the end of June 2028. The latest rock collapse is a separate incident; its cause and effect on the schedule remain under assessment.
KP Proposes Rs160.18 Billion Development Package for Roads, Infrastructure and Public Facilities

KP Proposes Rs160.18 Billion Development Package for Roads, Infrastructure and Public Facilities

▫️ Road expansion, new schools, healthcare facilities and infrastructure improvements among key priorities

Peshawar | ReNews KP CorrespondentThe Khyber Pakhtunkhwa government has proposed a Rs160.18 billion development package aimed at improving road infrastructure, public facilities, education, healthcare and security across 37 districts. Un...

World Bank Upgrades Punjab Land Records Digitisation Project Rating to Highly Satisfactory

World Bank Upgrades Punjab Land Records Digitisation Project Rating to Highly Satisfactory

▫️ Punjab exceeds major land reform targets, with 69.92 million land rights registered and digital cadastral maps covering 86% of the province

The World Bank has upgraded the Punjab Urban Land Systems Enhancement Project's development and implementation ratings from Satisfactory to Highly Satisfactory after several key targets were exceeded.

Pakistan Pushes Regional Transport Infrastructure Development to Strengthen Trade Connectivity

Pakistan Pushes Regional Transport Infrastructure Development to Strengthen Trade Connectivity

▫️ Federal Minister Abdul Aleem Khan highlights CPEC road projects, M-6 Motorway financing and cross border railway links at UN ESCAP conference in Bangkok

Federal Minister for Communications Abdul Aleem Khan has called for stronger regional transport infrastructure and alternative trade corridors to improve connectivity between Central Asia, South Asia, China and the Middle East.

Government Approves 25-Year Public-Private Partnership for Two Sections of Sukkur Hyderabad M 6 Motorway

Government Approves 25-Year Public-Private Partnership for Two Sections of Sukkur Hyderabad M 6 Motorway

▫️Public Private Partnership Authority (P3A) Board approves separate concession agreements for 121 kilometres of motorway, allowing private investors to finance, construct and operate both sections

The Public Private Partnership Authority (P3A) Board has approved separate concession agreements for the development of Sections I and II of the Sukkur Hyderabad M 6 Motorway, covering a combined distance of 121 kilometres.

Federal Constitutional Court Dismisses LDA Appeal in 14 Marla Gulberg III Property Dispute

Federal Constitutional Court Dismisses LDA Appeal in 14 Marla Gulberg III Property Dispute

▫️ Court directs LDA to avoid wasting public funds on unnecessary litigation after repeated legal challenges over disputed land

Islamabad | ReNews National CorrespondentThe Federal Constitutional Court (FCC) has dismissed an appeal filed by the Lahore Development Authority (LDA) concerning a 14 marla property in Lahore’s Gulberg III area.

CDA Completes Over 96% Construction Work on 11-Storey National Police Academy in Islamabad

CDA Completes Over 96% Construction Work on 11-Storey National Police Academy in Islamabad

▫️ Modern training facility features 126 rooms, jogging track, rappelling towers and obstacle courses; major construction completed within 15 months

The Capital Development Authority (CDA) has completed more than 96% of construction work on the 11-storey National Police Academy building in Islamabad's Sector H 11.

CDA Issues Show Cause Notice to Jinnah Garden Phase II Over Illegal Development Along Soan River

CDA Issues Show Cause Notice to Jinnah Garden Phase II Over Illegal Development Along Soan River

▫️ Housing scheme accused of carrying out development without CDA approval and constructing a 1,200 foot wall, partly outside its approved boundaries.

The Capital Development Authority (CDA) has issued a show cause notice to Jinnah Garden Phase II on Kahuta Road in Islamabad’s Zone 5 over alleged unauthorised development and construction along the Soan River.

State Bank Issues New Financing Guidelines for REITs, Builders and Developers

State Bank Issues New Financing Guidelines for REITs, Builders and Developers

▫️ New regulations introduce property valuation requirements, construction monitoring and mandatory insurance or Takaful coverage for development projects

The State Bank of Pakistan (SBP) has introduced new financing guidelines for Real Estate Investment Trusts (REITs), builders and property developers to improve access to financing while strengthening risk management.

World Toilet Day Highlights Pakistan’s Sanitation Crisis as Millions Lack Safe Facilities

World Toilet Day Highlights Pakistan’s Sanitation Crisis as Millions Lack Safe Facilities

▫️ Over 58% of rural Pakistan lacks safely managed sanitation services, while 25 million people still practise open defecation

Pakistan joins the international community in observing World Toilet Day on November 19, drawing attention to the continuing shortage of safe sanitation facilities.

More Real Estate News

City and District Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →