PPIB Puts three 1,832MW  Hydropower Projects on Hold as Rooftop Solar Slows Electricity Demand Growth

PPIB Puts three 1,832MW Hydropower Projects on Hold as Rooftop Solar Slows Electricity Demand Growth

▫️Azad Pattan, Kohala and Kathai II projects face prolonged delays after failing to achieve financial close, while planners reassess their role under the IGCEP 2025 2035

Islamabad | ReNews PakistanThe Private Power and Infrastructure Board (PPIB) has decided to place three hydropower projects with a combined generation capacity of 1,832 megawatts on hold after determining that they no longer qualify unde...

Islamabad | ReNews Pakistan
The Private Power and Infrastructure Board (PPIB) has decided to place three hydropower projects with a combined generation capacity of 1,832 megawatts on hold after determining that they no longer qualify under the least cost optimisation framework of the Indicative Generation Capacity Expansion Plan (IGCEP) 2025 2035. The decision comes amid slowing electricity demand growth, which officials attribute largely to the rapid expansion of rooftop solar installations across the country.
According to observations made during the audit of the PPIB for the financial year 2024 25, the three projects 700.7MW Azad Pattan Hydropower Project, 1,124MW Kohala Hydropower Project and 8MW Kathai II Hydropower Project remained unimplemented after repeated delays in achieving financial close despite multiple extensions granted by the board.
The audit noted that the Letter of Support (LoS) for the Azad Pattan Hydropower Project was issued on June 30, 2016. However, the project failed to reach financial close by December 31, 2024, despite receiving five extensions, primarily because of financing constraints linked to China's export credit insurer, Sinosure.
The project sponsor later requested an additional extension until December 2027. During its 148th meeting held on August 1, 2025, the PPIB Board decided to maintain the existing status of the project while awaiting the outcome of the CPEC Energy Cooperation List Adjustment Joint Study. The board also noted that the project had not been selected under the draft IGCEP 2025–2035 least cost optimisation process.
Similarly, the Kohala Hydropower Project, which received its Letter of Support on December 31, 2015, has also been unable to achieve financial close despite several extensions that remain valid until September 30, 2027. Like Azad Pattan, the project was excluded from the draft IGCEP because it did not meet the revised least cost planning criteria.
The smallest of the three schemes, the 8MW Kathai II Hydropower Project, was issued its Letter of Support on November 20, 2019. However, the project encountered prolonged delays due to the non availability and delayed approval of standardised security package documents, which required clearance from the Economic Coordination Committee (ECC) and the Cabinet Committee on Energy (CCoE).
As a result, the PPIB Board approved the cancellation of the project's Letter of Support by mutual consent in August 2025. The audit observed that the cancellation highlighted broader regulatory and institutional facilitation gaps that were subsequently communicated to the relevant ministry in December 2025.
In its response to the audit, PPIB management stated that both the Azad Pattan and Kohala hydropower projects were excluded from the IGCEP 2025–2035 because of declining electricity demand projections driven by the rapid adoption of rooftop solar systems across Pakistan.
The development reflects a significant shift in the country's power sector planning, where changing consumption patterns, distributed renewable energy generation and least cost optimisation are increasingly influencing investment decisions for large scale electricity projects. While hydropower remains a key component of Pakistan's long term energy strategy, future project implementation is expected to depend on updated demand forecasts, financing availability and national generation planning priorities.
More Than 340,000 Kanals of Auqaf Land Missing from Official Records in Khyber Pakhtunkhwa

More Than 340,000 Kanals of Auqaf Land Missing from Official Records in Khyber Pakhtunkhwa

▫️ The Auqaf Department’s records list around 67,000 kanals across the province, while administrations in 20 districts have reported a total of 407,374 kanals and eight marlas; Officials fear influential individuals may have occupied land absent from the department’s records

More than 340,000 kanals of Auqaf land in Khyber Pakhtunkhwa are missing from the department’s official records, even though administrations in 20 districts have reported a total of 407,374 kanals and eight marlas.

KP Workers Welfare Board Ordered to Remove Land Encroachments, Ensure Transparent Allotment of 496 Residential Flats

KP Workers Welfare Board Ordered to Remove Land Encroachments, Ensure Transparent Allotment of 496 Residential Flats

▫️ Governor’s adviser Amir Javed directs removal of encroachments within seven days, rules out direct housing allotments and orders digitisation of property records and stronger administrative oversight

Khyber Pakhtunkhwa Governor’s Adviser on Law, Labour and Inter-Provincial Coordination Amir Javed has directed the Workers Welfare Board (WWB) to ensure transparent allotment of residential flats, remove encroachments from its properties...

SHC Orders Recovery of 25 Acres of Encroached Public Land in Karachi’s Orangi Town

SHC Orders Recovery of 25 Acres of Encroached Public Land in Karachi’s Orangi Town

▫️ Karachi mayor directed to cancel illegal leases, initiate civil, criminal and departmental proceedings against those responsible, and submit a detailed compliance report within 30 days

The Sindh High Court (SHC) has directed the Karachi mayor to take immediate and effective measures to recover approximately 25 acres of valuable public amenity land in Orangi Town, expressing serious dissatisfaction over the Karachi Metr...

SECP Urges Businesses to Insure Property and Assets Against Fire Risks

SECP Urges Businesses to Insure Property and Assets Against Fire Risks

▫️ Business owners and industrialists were briefed on property insurance, business interruption protection, Takaful and the claims process

The Securities and Exchange Commission of Pakistan (SECP) has urged businesses to consider fire and property insurance to protect their assets from unexpected damage and reduce the financial impact of potential losses.

Senate Committee Uncovers 27 Allegedly Illegal Housing Societies on Jammu and Kashmir State Land in Lahore

Senate Committee Uncovers 27 Allegedly Illegal Housing Societies on Jammu and Kashmir State Land in Lahore

▫️ Senate delegation inspects state-owned properties in Sultanpura, Rehmanpura and Naulakha Bazaar amid concerns over unauthorised housing developments and land encroachments

A Senate sub-committee has raised serious concerns over the reported establishment of 27 allegedly illegal housing societies on land belonging to Jammu and Kashmir State in Lahore, where residential plots are reportedly being sold to uns...

More Real Estate News

City and District Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →