Published: February 16, 2026 - 11:47 AM
RCC Phase to Commence at Diamer-Basha and Dasu as Structural Development Enters Key Stage.
دیامر بھاشا اور داسو منصوبے تعمیراتی اعتبار سے اہم مرحلے میں داخل، مرکزی کنکریٹ ورک رواں سال شروع ہوگا.
▫️ Major concrete placement scheduled following completion of excavation and preparatory milestones ▫️ Parallel development of residential settlements and civic infrastructure progressing in surrounding areas
Gilgit | ReNews Pakistan The Water and Power Development Authority (WAPDA) has announced that roller-compacted concrete (RCC) works at the Diamer-Basha Dam and Dasu Hydropower Project will commence during the current year, marking a s...
The Water and Power Development Authority (WAPDA) has announced that roller-compacted concrete (RCC) works at the Diamer-Basha Dam and Dasu Hydropower Project will commence during the current year, marking a significant transition from foundation preparation to structural construction. The development follows substantial progress in excavation, engineering preparation, and installation of essential construction systems.
The update was shared during WAPDA Chairman Lt Gen (Retd) Muhammad Saeed’s visit to both project sites, where he reviewed implementation progress and directed project teams to maintain construction timelines and ensure adherence to approved execution plans.
At Diamer-Basha Dam, located on the Indus River near Chilas, excavation of key structural foundations, including the dam base and abutments, has largely been completed. RCC trial operations have been conducted successfully, enabling the project to proceed toward full-scale concrete placement. Construction activity is currently ongoing across approximately 20 operational zones. The project remains on track for completion in 2030.
Supporting development in nearby localities is also advancing. A cadet college in Chilas has been completed, while work on the Harpan Das model village has reached approximately 61 per cent completion. Infrastructure development, including internal road networks, water supply systems, and sanitation facilities, is underway. Additional public service projects, including a water supply scheme for Chilas and a health facility in Upper Kohistan, are in various stages of implementation.
At the Dasu Hydropower Project, construction is progressing across 23 active sites, including underground power generation chambers and structural foundations. Concrete production plants are fully operational, enabling the project to proceed with RCC placement during the current year. A dedicated 132 kV transmission line constructed to support project operations is in its final commissioning phase. Power generation from the project is scheduled to begin in 2028.
Both projects represent critical components of Pakistan’s long-term infrastructure expansion strategy, with associated settlement development, transport connectivity, and public service facilities expected to support regional growth and long-term economic integration.