Red Line BRT Revival Phase: Sindh Government Hands Project to FWO, Sets 3 Month Completion Target
ریڈ لائن بی آر ٹی کی بحالی کا نیا مرحلہ: سندھ حکومت نے منصوبہ ایف ڈبلیو او کے حوالے کر دیا
▫️Long delayed transport project reenters fast track construction phase amid renewed government push
Karachi | ReNews Pakistan The Sindh government has once again decided to reactivate the long delayed Bus Rapid Transit (BRT) Red Line project by handing over its execution to the Frontier Works Organization (FWO), setting a 90 day dea...
The Sindh government has once again decided to reactivate the long delayed Bus Rapid Transit (BRT) Red Line project by handing over its execution to the Frontier Works Organization (FWO), setting a 90 day deadline for the completion of key components.
On the directives of Chief Minister Murad Ali Shah, construction activity has resumed on previously stalled sections of the project, particularly along University Road. The provincial government has instructed that the mixed-traffic corridor and drainage system be completed within three months in order to reduce public inconvenience.
The decision came after the office of the previous contractor was sealed, prompting the government to transfer the project to FWO on an emergency basis. According to official sources, the move reflects administrative seriousness as well as growing public pressure, as the project has remained delayed for several years.
Chief Minister Murad Ali Shah has directed that construction work continue even during the Eid holidays to ensure that targets are met within the stipulated timeframe.
Government sources say that work on both sides of Lot II has been targeted for completion within 90 days, with priority being given to the most affected stretches.
Construction of water pipelines, service roads, and drainage infrastructure has been targeted for completion by the end of July. These areas have long been a major source of traffic congestion and public inconvenience.
Karachi Mayor Murtaza Wahab confirmed on the social media platform X that FWO has resumed work on University Road. He stated that the Chief Minister has clearly directed that the mixed traffic corridor and drainage works must be completed within 90 days.
During a visit to the project site, the Chief Minister expressed regret over the delays and apologized to citizens for the prolonged inconvenience. He said that approximately 12 kilometers of mixed traffic lanes would be restored within three months, adding that resolving public hardship remains the government’s top priority.
He further announced that the tender for the main corridor of Lot II will be reissued. He added that discussions with the FWO leadership have been completed and full scale construction activities are expected to resume within the next two to three days.
The Red Line BRT project was launched in 2022 with an estimated cost of Rs77–80 billion; however, due to delays and various disputes, the cost has now exceeded Rs103 billion. Disagreements over funding and construction quality with the previous contractor had significantly slowed progress.
Over the past four years, the incomplete project has severely affected daily life in Karachi. The prolonged delays have drawn continuous criticism from citizens, while the project has frequently been mocked on social media for its slow progress and repeated disruptions.