Senate Panel Cancels Bids for Rs 26 Billion Nowshera Chitral Highway Project Over Procurement Irregularities
سینیٹ کمیٹی نے 26 ارب روپے کے نوشہرہ، چترال ہائی وے منصوبے کی بولیاں منسوخ کر دیں
▫️Committee raises concerns over inflated bid, project delays and foreign funded development schemes in Khyber Pakhtunkhwa
Islamabad | ReNews Pakistan A Senate committee has ordered the cancellation of the bidding process for the Rs 26 billion Nowshera Chitral highway project in Khyber Pakhtunkhwa after identifying serious irregularities in the procuremen...
A Senate committee has ordered the cancellation of the bidding process for the Rs 26 billion Nowshera Chitral highway project in Khyber Pakhtunkhwa after identifying serious irregularities in the procurement procedure.
The directive was issued during a meeting of the Senate Standing Committee on Economic Affairs, chaired by Senator Saifullah Abro. The committee declared the bidding process for the N-45 highway project null and void and instructed the National Highway Authority to begin a fresh bidding process within 30 days.
According to the committee, the new process must ensure complete transparency in both technical and financial evaluation. Officials were also directed to follow the two-envelope bidding procedure and make all relevant bidding documents available for scrutiny.
The controversy mainly relates to the Kalatak Chitral section of the project, covering around 47.98 kilometres. The committee was informed that a single bid submitted by M/s Sambu Engineering was 224 percent higher than the engineer’s estimate, raising serious questions about the fairness and competitiveness of the procurement process.
The project, estimated at around $93.7 million, is being financed through a Korean loan. However, committee members expressed concern that loan conditions appeared to favour contractors from the lending country, limiting competition and raising transparency concerns.
During the meeting, members also expressed dissatisfaction over the non-disclosure of bidding documents, lack of clarity regarding the eligibility of participating companies, and the failure of NHA officials to properly respond to committee queries.
The committee also questioned ongoing negotiations with Korean authorities to allow joint ventures between Korean and Pakistani firms, stressing that all such arrangements must be handled transparently and in the national interest.
Lawmakers further noted that the project was initiated in 2021, but construction work has still not begun. They expressed concern that important sections, including Timergara Chakdara, remain neglected despite their importance for regional connectivity and public mobility.
To examine broader issues in foreign funded development projects, the committee formed a sub-committee to review budget utilisation, causes of delays, and the accountability of officials responsible for slow implementation.
Separately, the panel also sought records related to the auction of public-sector power plants. Members raised concerns over the Asian Development Bank’s policy of not financing coal based projects, which has affected funding for projects such as the Jamshoro power project.