Rawalpindi Underpass Projects Near Completion as Race Course Reaches 74% and Charing Cross 71%
راولپنڈی میں دو اہم انڈر پاسز کی تعمیر تکمیل کے قریب، ریس کورس کا 74 فیصد اور چیئرنگ کراس کا 71 فیصد کام مکمل
▫️ Commissioner Salman Ghani reviews construction progress on Peshawar Road, directs authorities to complete remaining underpass work by the end of November
Construction work on two major underpasses along Peshawar Road in Rawalpindi is progressing towards completion, with the Race Course Chowk Underpass reaching 74% and the Charing Cross Underpass 71%.
Officials informed the commissioner that major works, including piling, deck slabs, excavation, utility relocation and drainage infrastructure, were nearly complete. The Race Course Underpass will feature two northbound lanes and a three level road arrangement to improve traffic movement. Once operational, both underpasses are expected to reduce congestion and create an almost signal-free traffic corridor along Peshawar Road.
The commissioner also inspected the 6,100 foot drainage project being constructed by the Water and Sanitation Agency (WASA) in Ganjmandi under the Punjab Development Programme. WASA Managing Director Azizullah Khan reported that 1,400 feet of the drain had been completed. The commissioner directed authorities to accelerate construction, strengthen site safety measures and complete the remaining work by April 2027.