Published: April 28, 2026 - 5:20 PM
37% Work Completed on Bhatti Chowk Underpass, Piling Reaches 85%
بھاٹی چوک انڈر پاس کا 37 فیصد کام مکمل، پائل ورک 85 فیصد تک پہنچ گیا
▫️Data Darbar pedestrian zone and Railway Station parking area enter final stages of completion
Lahore: [Riaz Hussain ReNews] Director General LDA, Tahir Farooq, visited the ongoing development projects at the Data Darbar expansion scheme, Bhatti Chowk Underpass, and surrounding areas of the Railway Station, reviewing the progre...
Director General LDA, Tahir Farooq, visited the ongoing development projects at the Data Darbar expansion scheme, Bhatti Chowk Underpass, and surrounding areas of the Railway Station, reviewing the progress in detail.
During the visit, Chief Engineer TEPA Iqrar Hussain and Chief Engineer LDA Asrar Saeed briefed him that work on the pedestrian zone of the Data Darbar expansion project is nearing completion, while finishing work on the pedestrian underpass is continuing round the clock. Simultaneously, work on the parking area and the courtyard (piazza) of the shrine is also in progress.
The DG LDA also inspected the Bhatti Chowk Underpass project, where he was informed that overall 37% of the work has been completed, while 85% of the piling work has been achieved. On this occasion, he directed the contractor to expedite the pace of development work to ensure timely completion.
Later, he reviewed the ongoing development activities around the Railway Station. The briefing highlighted that development of the parking area in front of the station is in its final stages, with installation of solar lights and work on seating areas underway. Additionally, teams are actively working on façade upgradation along Circular Road and in the surrounding areas of the Railway Station.
DG LDA Tahir Farooq directed that progress on both projects should be regularly monitored and all work must be completed within the stipulated timeframe.