Published: March 17, 2026 - 12:57 PM
70% Work on Imdad Chowk to Akram Hospital Road Expected Before Eid
امداد چوک تا اکرم ہسپتال سڑک منصوبہ عید سے قبل 70 فیصد مکمل ہونے کا امکان
▫️ Progress Report Submitted in BHC, Court Orders Improved Traffic Management
Quetta: ReNews Pakistan The Balochistan High Court was informed during the hearing of a constitutional petition concerning ongoing road construction and traffic issues in Quetta that the Imdad Chowk to Akram Hospital road project is ...
The Balochistan High Court was informed during the hearing of a constitutional petition concerning ongoing road construction and traffic issues in Quetta that the Imdad Chowk to Akram Hospital road project is progressing rapidly, with approximately 70 percent of the work expected to be completed before Eid-ul-Fitr.
The hearing was presided over by a two-member bench of Chief Justice Balochistan High Court, Justice Muhammad Kamran Khan Malakhel, and Justice Muhammad Najmuddin Mengal. During the proceedings, Project Director Rafiq Baloch of the Chief Minister’s Quetta Development Package appeared alongside the Additional Advocate General and submitted a detailed progress report to the court.
Officials informed the court that under the project, the existing road will be completely rebuilt with an aggregate base and asphalt base course. Additionally, the construction includes U-turns, cross-drainage systems, and service roads under the flyovers.
Subordinate works under the project include curbstone installation, footpaths, lane markings, traffic signage, and street lighting, all of which are scheduled for completion by 30 April 2026.
During the hearing, it was noted that after the Zarghoon Road expansion and the proposed service road on the left side, traffic from the city’s southeast and western areas may face challenges, as each carriageway will have only three lanes, while peak-hour traffic exceeds 50,000 to 70,000 vehicles daily.
The Project Director suggested that the eastern section of the road be used as part of the main carriageway instead of a service road, and that regulatory signboards, lane dividers, and cat eyes be installed to better manage traffic flow.
The court issued interim orders directing the Deputy Commissioner Quetta, DIG Quetta Range, and SSP Traffic Police to ensure that during construction and after completion, no government or private entity is allowed to use Zarghoon Road or other under-construction roads for parking, ensuring smooth traffic movement in the area.