LDA City Development Picks Up Pace as 65% Work on Structure Plan Road Completed
ایل ڈی اے سٹی کی ترقیاتی رفتار تیز، سٹرکچر پلان روڈ کا 65 فیصد کام مکمل ہوگیا
▫️DG LDA Tahir Farooq reviews progress on underpass, infrastructure and land acquisition projects; directs officials to accelerate development work during current fiscal year
Lahore: [ReNews Pakistan]The Lahore Development Authority (LDA) has accelerated progress on ongoing development projects in LDA City, with 65 percent of work on the Structure Plan Road completed.
The Lahore Development Authority (LDA) has accelerated progress on ongoing development projects in LDA City, with 65 percent of work on the Structure Plan Road completed. The authority has also decided to further speed up development activities during the current fiscal year to ensure the early completion of the project and provide modern facilities to residents.
DG LDA Tahir Farooq made these remarks during his visit to LDA City, where he reviewed ongoing development work, infrastructure construction and progress on land acquisition. Chief Engineer LDA Israr Saeed, Director LDA City and other officials briefed him on the project’s progress.
Officials informed the DG that work was under way simultaneously on all three barrels of the underpass being built along the Structure Plan Road. Girders are being launched on two barrels, while roof work is in progress on the third. The first asphalt layer has been completed on the ramp on one side of the underpass, while work continues on the other side.
Tahir Farooq directed the relevant authorities to use all available resources to complete the underpass and Structure Plan Road within the stipulated timeframe. He also stressed that citizens constructing homes in different blocks of LDA City should be provided every possible facilitation to further boost construction activity.
Officials said infrastructure development in LDA City was progressing rapidly and possession of more blocks would soon be handed over to allottees. They added that preparations were also under way to bring commercial plots to the market, a move expected to encourage investment and commercial activity in the project.
The DG LDA also received a detailed briefing on the ongoing land acquisition process and instructed officials to complete all land-related matters transparently and without delay so that development work does not face any obstruction.
He said the completion of the Structure Plan Road would significantly reduce travel time between Johar Town and LDA City, enabling citizens to reach the project within minutes. The road is also expected to improve traffic flow and enhance the residential and commercial value of LDA City.
Additional DG Urban Planning, Chief Town Planner II, Director Engineering, Director Auction, Director Metropolitan Planning, Director Land Acquisition and other relevant officials were also present during the visit.