Back to home

City and District Real Estate News

851 news articles

Progress begins on Rs8 billion underpass project in Rawalpindi, tree relocation completed

Progress begins on Rs8 billion underpass project in Rawalpindi, tree relocation completed

▫️ Land along main artery cleared and prepared for utility corridor and construction ▫️ Replantation and green belt expansion planned after completion

Rawalpindi | ReNews Pakistan Development work has formally progressed on three underpasses worth Rs8 billion in the cantonment area of Rawalpindi, with land preparation and environmental adjustments completed along the main urban corr...

Rawalpindi | ReNews Pakistan
Development work has formally progressed on three underpasses worth Rs8 billion in the cantonment area of Rawalpindi, with land preparation and environmental adjustments completed along the main urban corridor to facilitate construction and infrastructure reorganisation.
According to the Rawalpindi Cantonment Board (RCB), a total of 469 trees and 715 shrubs located along Peshawar Road between Qasim Market and Chairing Cross were carefully relocated to nearby suitable locations. The relocation was carried out to clear land required for structural works while preserving environmental assets within the urban zone.
Officials confirmed that the relocated trees have been replanted in green belts and open land parcels where adequate space is available. Additionally, the board has prepared a replantation plan under which more than 400 mature native trees and shrubs will be planted at the original sites after construction is completed. Furthermore, 74 dead trees were removed, and in accordance with environmental guidelines, ten new trees will be planted for each removed tree to maintain ecological balance.
The underpass project includes development near Race Course Park, Army Graveyard, and Chairing Cross. As part of land preparation, underground utility corridors are being established to accommodate essential service infrastructure. The Frontier Works Organisation (FWO) has initiated construction of a dedicated utility corridor to facilitate organised relocation of service networks beneath the surface.
Utility relocation activities have also been completed by Islamabad Electric Supply Company (IESCO), while other service providers, including Sui Northern Gas Pipelines Limited (SNGPL) and Pakistan Telecommunication Company Limited (PTCL), are transferring their infrastructure to designated corridors to enable uninterrupted construction work.
Authorities stated that once utility relocation and site preparation are fully completed, full-scale construction will commence, with an estimated completion period of approximately 70 days. The project is expected to improve traffic flow, optimise land use along the corridor, and strengthen accessibility for surrounding commercial and residential zones.
AJK Assembly Welcomes 100-Day Development Plan for Infrastructure and Public Services

AJK Assembly Welcomes 100-Day Development Plan for Infrastructure and Public Services

▫️ Resolution highlights proposed improvements in road networks, healthcare, education, transport and tourism across Azad Kashmir

The Azad Jammu and Kashmir (AJK) Legislative Assembly has welcomed the announcement of a 100-day development plan aimed at improving infrastructure and public services across the region.

NHA to Construct 1.56 km Malupa Tunnel as Development Work Accelerates on Jaglot–Skardu Road

NHA to Construct 1.56 km Malupa Tunnel as Development Work Accelerates on Jaglot–Skardu Road

▫️ New tunnel, landslide protection structures, road lighting and rescue services planned to improve travel safety

Federal Minister for Communications Abdul Aleem Khan has inspected ongoing construction and infrastructure development projects along the Jaglot–Skardu Road in Gilgit-Baltistan.

CDA Approves Islamabad Avenue and Plans Commercial Development Along 3.8km Road

CDA Approves Islamabad Avenue and Plans Commercial Development Along 3.8km Road

▫️ New road linking Park Road with Margalla Enclave to feature commercial and mixed-use projects under proposed building regulations

Islamabad | ReNews Capital CorrespondentThe Capital Development Authority (CDA) Board has approved the name Islamabad Avenue for the 3.8-kilometre road under construction between Park Road and Margalla Enclave in Islamabad. The board als...

Federal Minister Orders Early Completion of Lowari Tunnel and Chitral Highway Projects

Federal Minister Orders Early Completion of Lowari Tunnel and Chitral Highway Projects

▫️ Completion of road projects aimed at improving regional connectivity, supporting tourism and facilitating local communities

Federal Minister for Communications Abdul Aleem Khan has directed the authorities concerned to accelerate the remaining construction and development works on the Lowari Tunnel and Chitral Highway projects.

LDA to Auction Commercial Plots in Lahore Technology Park on December 3

LDA to Auction Commercial Plots in Lahore Technology Park on December 3

▫️ Balloting for Pine Axis and Pine Executive plots scheduled for December 10 as LDA expands investment opportunities

The Lahore Development Authority (LDA) has announced that commercial plots in Lahore Technology Park, located on Ferozepur Road near Arfa Karim Software and Technology Tower, will be auctioned on December 3, 2026, at Expo Centre, Johar T...

KP Plans Independent Commission to Resolve Land Ownership Dispute Between Kolai-Palas and Battagram Tribes

KP Plans Independent Commission to Resolve Land Ownership Dispute Between Kolai-Palas and Battagram Tribes

▫️ Hazara administration to seek provincial approval for an impartial settlement commission to determine disputed land ownership

The Hazara divisional administration has decided to approach the Khyber Pakhtunkhwa government for the establishment of an independent settlement commission to resolve a longstanding land ownership dispute between rival tribes in Kolai-P...

FGEHA Approves Relocation of Three Islamabad Plots to Preserve 300-Year-Old Trees

FGEHA Approves Relocation of Three Islamabad Plots to Preserve 300-Year-Old Trees

▫️ Three one-kanal residential plots in Sector G-14/3 to be shifted as authority plans a park around two historic banyan trees

The Federal Government Employees Housing Authority (FGEHA) has approved in principle the relocation of three residential plots in Islamabad's Sector G-14/3 to protect two banyan trees estimated to be around 300 years old.

Pakistan Railways Issues Eviction Notices to 147 Property Owners in Hyderabad Over Land Ownership Dispute

Pakistan Railways Issues Eviction Notices to 147 Property Owners in Hyderabad Over Land Ownership Dispute

▫️ Railways claims more than 1,152 acres across Hyderabad district as property owners question eviction notices and demand legal protection

Pakistan Railways has issued approximately 147 eviction notices to owners and occupants of residential and commercial properties in Hyderabad, alleging unauthorised occupation of railway land.

Punjab Signs Agreements for Modern Toll Plazas on 318 Kilometres of Major Roads

Punjab Signs Agreements for Modern Toll Plazas on 318 Kilometres of Major Roads

▫️ Ten toll plazas to be developed across Muridke–Narowal–Shakargarh Road, Faisalabad–Samundri–Rajana Road and Faisalabad Ring Road

The Punjab government has signed agreements with private companies to develop and operate ten modern toll plazas across 318 kilometres of major road networks.

More City and District Real Estate News

More Real Estate News

National Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →