Published: April 27, 2026 - 3:44 PM
Rapid Pace of Development Projects in Gujranwala, Mega Schemes Worth Over Rs110 Billion Underway
گوجرانوالہ میں ترقیاتی منصوبوں کی رفتار تیز، 110 ارب روپے سے زائد کے میگا پراجیکٹس زیرِ تکمیل
▫️Significant progress in sanitation, rural development, and infrastructure schemes; Gujranwala outpaces other districts in the province
Lahore: [ReNews Pakistan] Gujranwala has taken a clear lead in the development race, surpassing other districts of Punjab, with mega projects worth over Rs110 billion progressing at a rapid pace.
Gujranwala has taken a clear lead in the development race, surpassing other districts of Punjab, with mega projects worth over Rs110 billion progressing at a rapid pace.
According to official data, Gujranwala’s development portfolio spans key sectors including transport, sanitation, rural development, urban rehabilitation, and inter-district connectivity. Officials say the pace of implementation is faster than in other districts, giving Gujranwala a prominent position.
The city’s largest project is a mass transit system worth Rs 62.738 billion, launched on February 15, 2026, and expected to be completed by December 5, 2026. For the current fiscal year, Rs 30 billion has been allocated, of which Rs 10 billion has already been released and fully utilized. The project has achieved 15% physical progress so far. Upon completion, it is expected to reduce traffic congestion and improve urban mobility.
In the sanitation sector, a Rs 30.129 billion program is underway under WASA, including improvements to the sewerage system, wastewater treatment plants, and road rehabilitation. The project has achieved 31% physical progress, while financial utilization stands at 18%.
Multiple sewerage projects are also in progress in Wazirabad, Ali Pur, and Kamoke, involving the construction of disposal stations and expansion of sewer networks. In some cases, financial utilization is high while physical progress remains in early stages, with expectations of acceleration in the coming months.
Under the “Model Village” program, several rural areas are being provided with improved water supply, drainage, and basic infrastructure, aiming to bring urban level facilities to rural communities.
Urban rehabilitation projects, particularly beautification schemes, are also making notable progress. These include the renovation of inner-city areas and commercial centers, with completion levels ranging from 45% to 69%, and deadlines expected to be met.
In the transport sector, projects such as the Kangniwala Flyover and the road from Awan Chowk to the M-2 Motorway via Nowshera Virkan are expected to significantly improve regional connectivity.
Officials state that timely fund releases, efficient utilization, and rapid implementation have placed Gujranwala at the forefront of Punjab’s development agenda. With major projects expected to be completed between late 2026 and mid-2027, significant improvements in transport, sanitation, and economic activity are anticipated.