Back to home

City and District Real Estate News

4 news articles

Rawalpindi Ring Road Phase II Feasibility Completed, Rs9 Billion Thallian/Hakla Expansion Emerges as Preferred Option

Rawalpindi Ring Road Phase II Feasibility Completed, Rs9 Billion Thallian/Hakla Expansion Emerges as Preferred Option

▫️NESPAK recommends widening the 15.3-kilometre M-2 motorway section from Thallian to Hakla from three to five lanes in each direction, making it the least-cost option among three proposed alignments

Rawalpindi : ReNews PakistanThe feasibility study for Phase-II of the Rawalpindi Ring Road has been completed, with NESPAK identifying the expansion of the existing M-2 motorway corridor between Thallian and Hakla Interchange as the most...

Rawalpindi : ReNews Pakistan
The feasibility study for Phase-II of the Rawalpindi Ring Road has been completed, with NESPAK identifying the expansion of the existing M-2 motorway corridor between Thallian and Hakla Interchange as the most feasible and least expensive of three proposed options.
Under the preferred alignment, the existing motorway section from Thallian to Hakla Interchange, which forms part of the China Pakistan Economic Corridor route, would be widened from three lanes to five lanes in each direction.
The proposed widening would cover approximately 15.3 kilometres and is estimated to cost around Rs 9 billion, significantly lower than the two alternative alignments examined during the feasibility process.
The second option proposes construction of an additional 19.5 kilometre route at an estimated cost of Rs18 billion, while the third option involves a 26.5 kilometre alignment on the western side of the motorway with a projected cost of around Rs 24 billion.
The assessment therefore places the first option at a clear cost advantage, while also allowing planners to use an existing major transport corridor instead of constructing an entirely new route.
The completion of the feasibility study represents an important step towards determining the future extension of the Rawalpindi Ring Road and improving connectivity between Thallian and Hakla. However, the preferred option will still require approval from the relevant authorities before implementation can begin.
Meanwhile, substantial progress has already been made on Phase-I of the project, which stretches approximately 38.3 kilometres from GT Road at Banth Mor to Thallian Interchange.
The main carriageway of Phase-I has largely been completed, while four of its five interchanges — Banth, Chakbeli Khan, Adiala and Chakri — have also been completed.
Work is continuing on the fifth interchange at Thallian after its design was expanded to provide broader connectivity. Despite the remaining work at the interchange, the Ring Road has already been connected with the motorway network.
Construction of toll plazas and installation of the tolling system are now among the major outstanding components of Phase-I.
Once the remaining toll-related infrastructure is completed, the project is expected to be transferred from the Project Management Unit to the Punjab Ring Road Authority, which will assume responsibility for its operation and management.
The Ring Road project has faced several revisions to its completion and inauguration schedule. August 14, 2026, had most recently been indicated as the expected inauguration date, but the opening did not take place because the tolling infrastructure had not yet been completed.
A service area established along the Ring Road, which had previously attracted controversy, has also been removed from the project route.
The proposed Phase-II extension is considered important for strengthening regional road connectivity by providing a more efficient link between the completed Ring Road corridor and the Hakla Interchange on the motorway network.
If the Rs 9 billion widening option receives final approval, the project would add two lanes in each direction along the 15.3 kilometre Thallian/Hakla section, potentially increasing traffic capacity while avoiding the substantially higher costs associated with constructing the two alternative routes.
The final alignment, funding mechanism and implementation schedule will depend on subsequent government approvals and decisions by the relevant project authorities.
Karachi Residents to Challenge Nehr-e-Khayyam Project in Court

Karachi Residents to Challenge Nehr-e-Khayyam Project in Court

▫️ Residents and Jamaat-e-Islami plan to petition the Sindh High Court, seeking protection of the canal’s natural waterway and adequate drainage to reduce flood risks

Karachi : ReNews District Correspondent Residents of Clifton and Defence, together with Jamaat-e-Islami, plan to approach the Sindh High Court to challenge the Nehr-e-Khayyam project, citing concerns about its impact on drainage and the ...

Excavation Near Islamabad Girls’ School Raises Safety Concerns

Excavation Near Islamabad Girls’ School Raises Safety Concerns

▫️ FDE says soil removal on three sides of the Kurri school has weakened its foundation and exposed the building to a steep drop

Islamabad | ReNews District Correspondent A government-run girls’ school in Islamabad’s Kurri area is facing safety concerns after excavation work nearby left the building exposed on three sides, according to the Federal Directorate of E...

LDA Allots Plot Numbers to 68 Successful Candidates

LDA Allots Plot Numbers to 68 Successful Candidates

▫️ Candidates who paid a 20% down payment were allotted plots in Johar Town, LDA City and Avenue One

Lahore | Riaz Hussain, Chief Reporter, ReNews PakistanPlot numbers have been allotted to successful candidates in the sixth draw for commercial and residential plots, held on September 9 on the directions of Lahore Development Authority ...

Islamabad : Kashmir Chowk Underpass 78% Complete After 20 Days

Islamabad : Kashmir Chowk Underpass 78% Complete After 20 Days

▫️ Plans include planting 6,000 trees and adding landscaping and decorative lighting around the underpassIslamabad : ReNews District Correspondent Work on Islamabad’s Kashmir Chowk Underpass has reached 78% completion in 20 days, Interior Minister Mohsin Naqvi said during a visit to the project site.

Islamabad : ReNews District Correspondent Work on Islamabad’s Kashmir Chowk Underpass has reached 78% completion in 20 days, Interior Minister Mohsin Naqvi said during a visit to the project site.

More City and District Real Estate News

More Real Estate News

National Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →