Malaysian Appellate Court Upholds Covid-Era Housing Deadline Extension Law
ملائیشیا: اپیلیٹ کورٹ نے کووڈ دور کے ہاؤسنگ ڈیڈ لائن توسیعی قانون کو برقرار رکھنے کو درست قرار دیدیا
▫️Judges hold the law was a temporary pandemic relief measure, not a benefit for delayed or defaulting developers
Kuala Lumpur | ReNews International Desk News Malaysia’s Court of Appeal has upheld a Covid-era legal provision that allowed extensions for the delivery of vacant possession and completion of common facilities in housing projects, rul...
Malaysia’s Court of Appeal has upheld a Covid-era legal provision that allowed extensions for the delivery of vacant possession and completion of common facilities in housing projects, ruling that the measure is constitutional and does not violate property rights.
The appellate court held that Section 38C of the Temporary Measures for Reducing the Impact of Coronavirus Disease 2019 (Covid-19) (Amendment) Act 2022 was a temporary and targeted response to disruption caused by the pandemic. The court said such a measure could not be treated as a permanent interference with rights protected under the Federal Constitution.
The unanimous decision was delivered by a three-member panel led by Datuk Ravinthran Paramaguru, now a Federal Court judge, together with Court of Appeal judges Datuk Azizul Azmi Adnan and Datuk Ahmad Fairuz Zainol Abidin.
Reading the judgment, Ahmad Fairuz said constitutional rights are permanent, while the Covid-19 legislation was limited in purpose and duration. He observed that a temporary law, by its nature, cannot amount to a permanent intrusion into constitutional rights.
The appeal was filed by homeowners against Sime Darby Brunsfield Resort Sdn Bhd, the housing and local government minister, and the then director general of the National Housing Department, Datuk N Jayaselan. The ruling also applies to 10 other related appeals heard together over similar legal questions.
At the centre of the dispute was Section 38C, particularly subsection 38C(3), which states that the minister shall not consider an application if it is made after the expiry of the time for delivery of vacant possession or completion of common facilities specified in the sale and purchase agreement.
The court clarified that the law was not designed to give developers an unfair advantage. It said the provision applied only to housing projects that were actively under construction and genuinely affected by pandemic restrictions. It was not meant to protect projects already delayed, abandoned, or facing problems for reasons unrelated to Covid-19.
The homeowners argued that the law affected their right to claim liquidated ascertained damages, commonly known as LAD, without adequate compensation, and therefore violated Article 13(2) of the Federal Constitution. The court rejected this argument.
Ahmad Fairuz said Section 38C did not transfer any property from purchasers to the developer or the state. He said the homeowners’ LAD rights were not permanently extinguished, but suspended for a defined period.
The court further said LAD is mainly a contractual remedy under a sale and purchase agreement, and a breach of contract does not automatically become a violation of constitutional property rights.
The judges also noted that earlier Covid related exemptions had already shifted the original contractual timeline. The panel found that the developer’s third exemption was properly granted because the application was made before vacant possession had been delivered and was supported by evidence of pandemic-related disruption.
The court concluded that Section 38C was proportionate and not arbitrary, saying its objective was to prevent wider damage to Malaysia’s housing construction sector during an unprecedented public health crisis, while also protecting purchasers from the risk of abandoned housing projects.