Government Weighs Revamp of Rs 130 Billion Peshawar Torkham Motorway Project
پشاور طورخم موٹروے منصوبے کی ازسر نو تشکیل پر غور، لاگت 130 ارب روپے تک پہنچ گئی
▫️Revised plan may remove Southern Link Road and divide the expressway into three construction packages
Islamabad | ReNews Pakistan The federal government is considering a major restructuring of the long delayed Peshawar Torkham Motorway project after repeated bidding failures, weak implementation progress and a sharp rise in estimated cos...
The federal government is considering a major restructuring of the long delayed Peshawar Torkham Motorway project after repeated bidding failures, weak implementation progress and a sharp rise in estimated cost pushed the project value close to Rs. 130 billion.
The 47 kilometer motorway is being financed through a $460 million World Bank loan signed in December 2019 under the Khyber Pakhtunkhwa Economic Corridor initiative. The project was initially estimated at Rs 41.44 billion and was expected to improve trade and transport connectivity between Peshawar, Torkham and the wider Peshawar Jalalabad Kabul corridor. However, construction has still not started, even though the loan reached its closing date on May 28, 2026.
Under the original design, the motorway also included a 55 kilometer Southern Link Road to connect the expressway with the N 55 highway at Badhbher and further link it with the N 5 highway between Chamkani and Jhagra. The link road was intended to strengthen regional access and support cargo movement along key national and cross border routes.
According to official documents, the Central Development Working Party approved a revised implementation strategy last month. Under the updated proposal, the Southern Link Road would be removed from the scope of work, while the 45 kilometer expressway would be divided into three separate construction packages measuring approximately 14.3 kilometers, 15 kilometers and 15 kilometers.
Officials believe the revised structure could make the project more manageable, improve contractor participation and help address financing constraints that have repeatedly stalled the bidding process.
The Planning Commission has blamed the lack of progress on weak implementation capacity among major stakeholders, including the National Highway Authority, the Ministry of Communications, the Economic Affairs Division and the World Bank. The government is now negotiating an extension of the loan agreement to keep the project alive.
Planning documents show that tenders for the project were cancelled several times after bids exceeded the approved cost estimates and available loan financing. The original cost calculations were based on the National Highway Authority’s 2014 Composite Scheduled Rates, while a detailed design and updated cost estimate based on 2025 rates are still being finalized.
The project is considered strategically important for Pakistan’s regional trade network, particularly for strengthening road connectivity with Afghanistan and Central Asia. However, unless the financing, design and execution issues are resolved, the motorway may continue to face further delays despite its economic significance.