Hyderabad/Sukkur Motorway Moves Forward as NHA Prequalifies Eight Firms for Two Key Sections
حیدرآباد/سکھر موٹروے منصوبے میں اہم پیش رفت، این ایچ اے نے دو اہم سیکشنز کیلئے 8 کمپنیوں کو پری کوالیفائی کرلیا
▫️306 kilometre motorway will complete a critical missing link in Pakistan’s north south network, connecting Karachi with Lahore, Islamabad and Peshawar through continuous motorway infrastructure
Islamabad | ReNews PakistanThe long delayed Hyderabad/Sukkur Motorway (M-6) has moved a step closer to construction after the National Highway Authority (NHA) prequalified eight construction firms and joint ventures for two key sections ...
The long delayed Hyderabad/Sukkur Motorway (M-6) has moved a step closer to construction after the National Highway Authority (NHA) prequalified eight construction firms and joint ventures for two key sections of the 306-kilometre project.
The development represents progress towards reviving one of Pakistan’s most important pending motorway projects, which is designed to complete the missing link in the country’s north-south motorway network and provide continuous motorway connectivity between Karachi and major cities in Punjab and Khyber Pakhtunkhwa.
The prequalification process covers Section IV of the M-6, extending approximately 60.90 kilometres from Naushahro Feroze to Ranipur, and Section V, covering around 59.88 kilometres from Ranipur to Sukkur.
Together, the two sections account for nearly 121 kilometres, or almost 40 percent, of the entire Hyderabad-Sukkur Motorway.
The NHA initiated the prequalification process for the two sections in December 2025. A total of 16 construction firms and joint ventures submitted applications.
Following an evaluation by the NHA’s Procurement and Contracts section, eight applicants were disqualified while eight were declared prequalified to proceed to the next stage of the procurement process.
Among the firms and joint ventures identified in the available information as having prequalified are SAJCO-ZKB (JV), China Construction Third Engineering Bureau Group Corporation Limited, SGEG-Umer Jan (JV), China 20 Bureau Group Company Limited, Onur Taahhut Tasimacilik Insaat Ticaret ve Sanayi, and Matracon-ZTZS (JV).
The source material identifies six of the eight successful applicants by name.
A major factor supporting progress on the two sections is the availability of international financing. The Islamic Development Bank has committed financing for Sections IV and V, providing financial backing for construction of the motorway between Naushahro Feroze and Sukkur.
The complete M-6 has been divided into five sections: Hyderabad-Tando Adam, Tando Adam/Nawabshah, Nawabshah/Naushahro Feroze, Naushahro Feroze/Ranipur and Ranipur/Sukkur.
Financing arrangements have so far been secured for three of these sections. In addition to the Islamic Development Bank's support for Sections IV and V, the OPEC Fund has committed financing for Section III, which will connect Nawabshah with Naushahro Feroze.
The first two sections, covering Hyderabad/Tando Adam and Tando Adam-Nawabshah, are planned to be developed through the public-private partnership model.
The financing structure therefore combines international development funding with private sector participation in an effort to deliver the entire motorway corridor.
The 306-kilometre M-6 is planned as a greenfield motorway between Hyderabad and Sukkur and is considered strategically important because it would close the remaining motorway gap between Karachi and the country's existing motorway network.
Once completed, motorists travelling from Karachi would be able to use a continuous high-speed motorway corridor towards Sukkur and then connect with the existing M-5 Sukkur-Multan Motorway. From there, the motorway network provides onward connectivity towards Lahore, Islamabad and Peshawar.
The project is also expected to improve freight movement between Karachi's ports and major industrial, agricultural and commercial centres in the rest of the country, potentially reducing travel times and improving the efficiency of road-based logistics.
The M-6 project has, however, faced significant delays.
An earlier attempt to develop the motorway suffered a setback when the NHA terminated its contract with TECMC (Pvt) Ltd in December 2023. The contractor had failed to achieve financial close despite being granted two extensions, forcing authorities to reconsider the project's implementation and financing arrangements.
The latest prequalification process, together with financing commitments from international lenders, indicates renewed efforts to move the project towards construction.
The next major steps will involve completing the procurement process, selecting contractors and awarding construction contracts for the internationally financed sections.
Subject to timely completion of financing arrangements, procurement and construction, the Hyderabad-Sukkur Motorway is expected to be completed around 2029.
Completion of the M-6 would represent a major expansion of Pakistan's motorway infrastructure and, more importantly, remove one of the last major gaps preventing uninterrupted motorway connectivity between Karachi and the country's central and northern regions.