Neelum Jhelum Hydropower Project Suffers Rs 128 Billion Losses as Audit Exposes Operational and Financial Crisis

Neelum Jhelum Hydropower Project Suffers Rs 128 Billion Losses as Audit Exposes Operational and Financial Crisis

▫️Audit reveals Rs 267 billion in uninsured assets, missed power generation targets and growing liabilities that threaten the long term viability of the 969 megawatt hydropower project

Islamabad | ReNews PakistanPakistan's flagship Neelum Jhelum Hydropower Project has suffered financial losses exceeding Rs 128 billion during the fiscal year 2024 25, according to the latest audit conducted by the Auditor General of Paki...

Islamabad | ReNews Pakistan
Pakistan's flagship Neelum Jhelum Hydropower Project has suffered financial losses exceeding Rs 128 billion during the fiscal year 2024 25, according to the latest audit conducted by the Auditor General of Pakistan. The report paints a troubling picture of persistent operational failures, prolonged plant shutdowns, tunnel collapses, rising debt obligations and weak financial management that have significantly undermined the project's long term sustainability.
The audit states that the 969 megawatt hydropower project recorded a net loss of Rs 29.41 billion during the fiscal year, while business interruption losses reached Rs 99.18 billion following extended shutdowns caused by the collapse of the tailrace tunnel in 2022 and the headrace tunnel in May 2024. These disruptions kept the powerhouse out of operation for extended periods, resulting in substantial revenue losses.
According to the report, investigations into both tunnel collapses remain incomplete. Auditors found that project management failed to adequately address technical defects, renew essential insurance coverage or obtain compensation for losses resulting from the structural failures. During the review period, project assets worth approximately Rs 267 billion remained uninsured, exposing the project to significant financial risk.
The audit also highlighted the project's continued inability to achieve its planned electricity generation targets. Since its commissioning, the Neelum Jhelum Hydropower Project has never met its annual generation target of 5,150 gigawatt hours, including years when the plant was fully operational. The report attributes this underperformance to operational inefficiencies and recurring technical challenges.
Another major concern identified in the audit is the absence of an approved reference tariff from the National Electric Power Regulatory Authority, which resulted in an estimated Rs 77.35 billion regulatory revenue shortfall. The delayed tariff approval has further weakened the project's financial position and limited its ability to recover operational costs.
Financial indicators presented in the audit reveal a rapidly deteriorating balance sheet. As of June 30, 2025, the project's current liabilities exceeded its current assets by Rs 307.89 billion, largely due to debt repayment defaults and the reclassification of long term loans as current liabilities.
The report further notes that the project has fallen well short of recovering its original investment. Against an approved project cost of Rs 418.89 billion, only Rs 180.17 billion had been recovered by the end of FY2024 25. In addition, nearly 69 percent of receivables remained overdue for more than 120 days, reflecting serious weaknesses in cash flow management and revenue collection.
The Auditor General concluded that persistent underperformance in electricity generation, prolonged operational outages, delayed regulatory approvals, increasing debt burdens and inadequate risk management practices have prevented the Neelum Jhelum Hydropower Project from achieving its intended financial and operational objectives. The report calls attention to the urgent need for corrective measures to improve governance, strengthen technical oversight and restore the project's long term financial viability.
Government Plans $1 Billion Investment in LPG Infrastructure

Government Plans $1 Billion Investment in LPG Infrastructure

▫️ Import terminals, storage facilities, cylinders and distribution networks to be expanded over three to five years

The government has drawn up a plan to invest about $1 billion over the next three to five years to expand Pakistan’s liquefied petroleum gas (LPG) infrastructure amid rising demand and constraints in the existing supply chain.

Record of More Than 1 Million Acres in Thal Under NAB Investigation

Record of More Than 1 Million Acres in Thal Under NAB Investigation

▫️ Discrepancies of 552,602 acres found across five districts in land acquisition notifications, Board of Revenue and district records; inquiry also examines alleged bogus claims and illegal transfers

More than one million acres acquired for the development and settlement of Punjab’s Thal region have come under investigation by the National Accountability Bureau (NAB).

FBR Revises Property Valuation Rules for Islamabad’s Rural Areas and Abbottabad

FBR Revises Property Valuation Rules for Islamabad’s Rural Areas and Abbottabad

▫️

The Federal Board of Revenue (FBR) has revised property valuation rules for rural areas of the Islamabad Capital Territory (ICT) and issued a new schedule of fair market values for immovable property in Abbottabad.

Grid Constraints Add Rs 400 Billion to Pakistan’s Power Costs

Grid Constraints Add Rs 400 Billion to Pakistan’s Power Costs

▫️ Transmission bottlenecks limit the use of cheaper electricity from Thar coal, nuclear and wind sources; FPCCI warns that higher fixed charges could offset any relief from lower variable tariffs

Pakistan’s electricity consumers are facing billions of rupees in additional costs because transmission constraints are preventing cheaper power generated in Sindh and southern Pakistan from reaching major consumption centres in the north.

Punjab  Govt Orders Provincewide Ban on Crop Residue Burning to Curb Smog

Punjab Govt Orders Provincewide Ban on Crop Residue Burning to Curb Smog

▫️ Maryam Nawaz directs all deputy commissioners to enforce the ban and criticises delays in district beautification work

Punjab Chief Minister Maryam Nawaz Sharif has directed deputy commissioners across the province to enforce a complete ban on the burning of crop residue, saying the practice is adding to worsening air pollution and smog.

More Real Estate News

City and District Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →