Over 20 Major Karachi Roads to Be Excavated for Rs 72 Billion K-IV Water Project
کراچی میں 72 ارب روپے کے 'کے فور' منصوبے کیلئے 20 سے زائد اہم سڑکوں کی کھدائی کا فیصلہ
▫️ Pipeline installation across 96 kilometres of roads to begin in January 2027, with construction expected to take 22 months
Karachi | ReNews PakistanMore than 20 major roads across Karachi will undergo excavation beginning in January 2027 under the Rs 72 billion K-IV water supply augmentation project, aimed at strengthening the city's water distribution infra...
More than 20 major roads across Karachi will undergo excavation beginning in January 2027 under the Rs 72 billion K-IV water supply augmentation project, aimed at strengthening the city's water distribution infrastructure and improving access to drinking water in areas facing persistent shortages.
The extensive infrastructure development will involve laying water pipelines along approximately 96 kilometres of roads, with construction expected to continue for 22 months. The planned excavation has raised concerns about potential traffic congestion, disruption to commercial activities and inconvenience for residents and commuters in Pakistan's largest metropolitan city.
Briefing the media on the project's implementation, K-IV Project Manager Faisal Javed said the tendering process was underway and construction activities were scheduled to commence in January 2027.
He explained that excavation would be carried out in phases rather than simultaneously across all affected roads to minimise disruption to the city's transportation network.
Under the proposed construction strategy, contractors will excavate road sections measuring between one and three kilometres, install the required water pipelines and subsequently proceed to the next section.
Javed said the phased approach was designed to limit inconvenience to motorists, businesses and residential communities while maintaining progress on the water supply project.
The estimated cost of the K-IV augmentation pipelines stands at Rs 72 billion, although project authorities have acknowledged that the final expenditure could increase during implementation.
According to the project manager, two international financial institutions are supporting the scheme, while the Sindh government will contribute 20 percent of the required funding.
The involvement of international financial institutions is expected to provide financial support for the development of water distribution infrastructure intended to address Karachi's growing water supply requirements.
Addressing concerns regarding damage to existing roads, Javed assured that the project authorities would be responsible for restoring roads affected by excavation activities.
He said arrangements had also been made to cover payments associated with gas and electricity infrastructure that could be affected during pipeline installation.
The planned construction work is expected to require careful coordination with relevant utility providers and civic authorities, particularly in densely populated areas where underground infrastructure and heavy traffic present significant challenges.
Responding to concerns about possible delays, Javed maintained that the pipeline installation would be completed within the stipulated 22-month period.
Following completion, the infrastructure will be handed over to the relevant water corporation for operational management and distribution of the additional water supply.
The K-IV project is designed to bring an additional 250 million gallons of water per day from Keenjhar Lake to Karachi, providing an important opportunity to improve water availability in neighbourhoods experiencing severe shortages or lacking regular supplies.
Karachi has long faced challenges associated with inadequate water distribution infrastructure, increasing demand and uneven access to municipal water supplies.
The planned augmentation infrastructure is intended to strengthen the distribution network and help ensure that additional water reaches communities where existing supply arrangements remain insufficient.
While the project represents a significant investment in Karachi's essential infrastructure, its implementation will also present a major challenge for urban mobility as excavation activities progress across key roads over the nearly two-year construction period.
The success of the initiative will depend not only on timely pipeline installation but also on effective traffic management, restoration of damaged roads and the eventual delivery of additional water to underserved communities.