Back to home

National Real Estate News

1 news article

Senate Committee Bars FGEHA from Launching New Housing Projects Until Existing Schemes Are Completed

Senate Committee Bars FGEHA from Launching New Housing Projects Until Existing Schemes Are Completed

▫️Housing Ministry cites litigation, land disputes, NAB inquiries, contractual issues and rising construction costs as key reasons behind slow progress

Islamabad | ReNews PakistanThe Senate Standing Committee on Housing and Works has directed the Federal Government Employees Housing Authority (FGEHA) not to launch any new housing projects until all ongoing schemes are completed, followi...

Islamabad | ReNews Pakistan
The Senate Standing Committee on Housing and Works has directed the Federal Government Employees Housing Authority (FGEHA) not to launch any new housing projects until all ongoing schemes are completed, following growing concerns over prolonged delays that have affected thousands of allottees, particularly retired government employees.
The committee, chaired by Senator Nasir Mehmood, was informed during its meeting that the Ministry of Housing and Works has imposed a restriction on the initiation of new FGEHA projects until the authority completes its existing developments.
Members of the committee expressed dissatisfaction over the pace of work, noting that none of the authority’s major housing schemes had been completed within the promised timelines. The panel stressed that project delays have undermined public confidence and created financial and administrative hardships for plot owners.
The committee reviewed the status of the Bhara Kahu Green Enclave-I housing scheme, which was launched in 2009. Officials informed lawmakers that only 52 percent of the development work has been completed after more than 17 years.
According to officials from the Ministry of Housing and Works and FGEHA, the project has faced multiple challenges, including prolonged litigation, inquiries by the National Accountability Bureau (NAB), land acquisition disputes, issues related to bank guarantees, contractual complications and a sharp increase in construction costs following the COVID-19 pandemic. They added that development work has resumed and several pending matters will be presented before the FGEHA Board for policy decisions.
Representatives of Green Enclave-I allottees also appeared before the committee and highlighted the prolonged uncertainty, financial burden and difficulties faced by plot owners due to repeated project delays.
Senator Nasir Mehmood questioned why contractual arrangements had continued despite years of slow progress and emphasized that thousands of citizens who invested their savings in the scheme deserve timely possession of their plots.
The committee directed that the project's contractor, Dr. Hafeez Abbasi, be summoned at the next meeting to explain the reasons behind the continued delays. It also urged all stakeholders, including the contractor and FGEHA management, to cooperate in resolving outstanding issues and ensuring the early completion of the long-delayed housing project.
KP Proposes Rs160.18 Billion Development Package for Roads, Infrastructure and Public Facilities

KP Proposes Rs160.18 Billion Development Package for Roads, Infrastructure and Public Facilities

▫️ Road expansion, new schools, healthcare facilities and infrastructure improvements among key priorities

Peshawar | ReNews KP CorrespondentThe Khyber Pakhtunkhwa government has proposed a Rs160.18 billion development package aimed at improving road infrastructure, public facilities, education, healthcare and security across 37 districts. Un...

More Real Estate News

City and District Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →