Senate Committee Directs FGEHA to Complete Green Enclave-I Within 18 Months
سینیٹ کمیٹی کی ایف جی ای ایچ اے کو گرین انکلیو ون 18 ماہ میں مکمل کرنے کی ہدایت
▫️Committee raises concerns over prolonged delays and disputed land in Sky Gardens, orders transparent NAB inquiry
Islamabad | ReNews PakistanThe Senate Standing Committee on Housing and Works has directed the Federal Government Employees Housing Authority (FGEHA) to ensure completion of the stalled Green Enclave-I housing project in Bhara Kahu withi...
The Senate Standing Committee on Housing and Works has directed the Federal Government Employees Housing Authority (FGEHA) to ensure completion of the stalled Green Enclave-I housing project in Bhara Kahu within 18 months, bringing renewed hope to hundreds of affected allottees.
The committee, chaired by Senator Nasir Mehmood, reviewed the long-delayed housing scheme, which was launched in 2009. FGEHA informed the committee that negotiations with its joint venture (JV) partner had been concluded and approval from the FGEHA Board was awaited regarding the escalation in project costs. The JV partner assured the committee that development work on Green Enclave-I would be completed within 18 months.
Following assurances from the Housing Secretary and the JV partner, the committee chairman formally directed that the project be completed within the stipulated period.
The committee expressed serious concern over the prolonged delay, noting that the stalled project had resulted in significant cost escalation and hardship for allottees. Members also questioned the performance of the JV partner and its ability to fulfil contractual obligations, particularly in view of the project's long delay.
It was further noted that FGEHA had not invoked any penalty clause against the JV partner despite the delays. Although the land had already been transferred to FGEHA, development and construction activities remained stalled for years.
The committee was informed that a third-party assessment of the ongoing construction had been conducted by a consultant, while funds released for the project corresponded to approximately 52 per cent of the work completed.
The National Accountability Bureau (NAB) told the committee that an earlier inquiry into the project had been quashed after clearance from the Supreme Court in 2018. Allottees welcomed the Senate committee's intervention, saying the 18-month completion assurance had restored their hopes of finally receiving the promised development.
The committee also examined allegations concerning the inclusion of Shamilaat and forest land in FGEHA's Sky Gardens housing scheme, located near Green Enclave-I.
NAB informed the committee that its inquiry into the alleged inclusion of Shamilaat land in Mouza Mengal had been reopened after FGEHA issued an addendum incorporating the area into the Sky Gardens development works.
FGEHA maintained that the Assistant Collector and Additional Deputy Commissioner Revenue had ruled in its favour, determining that the disputed land was settled land rather than Shamilaat. However, the Secretary Housing informed the committee that development on approximately 2,600 kanals had been halted and assured that no construction would take place on the disputed land until a final determination.
The matter is currently pending before the Senior Member Board of Revenue. FGEHA also said an interpretation of the relevant Supreme Court judgment would be sought through the Federal Constitutional Court.
The committee chairman directed NAB to conduct an impartial, transparent and merit-based inquiry into the disputed land issue.
Clarify the 52 per cent completion figure
Separate the two committee actions
Reduce repetition around project delays