Published: April 28, 2026 - 10:30 AM
Serious Allegations Surface in Rs 20 Billion Airport E gate Project, Contract Under Scrutiny for Procurement Rule Violations
20 ارب روپے کے ایئرپورٹ ای گیٹ منصوبے پر سنگین الزامات، ٹھیکہ قواعد کی خلاف ورزیوں کی زد میں
▫️Transparency International calls for open tendering, expresses concern over missing documents and alleged cost irregularities
Islamabad | ReNews Pakistan A Rs 20 billion contract for the installation of Egates at major airports across Pakistan has come under serious scrutiny after Transparency International Pakistan raised concerns over alleged violations of...
A Rs 20 billion contract for the installation of Egates at major airports across Pakistan has come under serious scrutiny after Transparency International Pakistan raised concerns over alleged violations of public procurement rules.
In a letter dated April 27 addressed to the Director General of the Pakistan Airports Authority, the organisation highlighted a complaint claiming that the contract was awarded without an open and competitive bidding process. The complaint alleges that the authority may have misused Rule 42(f) of the Public Procurement Rules 2004 to justify the award.
According to the letter, the contract was reportedly granted to a preselected group, bypassing mandatory requirements for open competition. The complainant further argued that Rule 42(f) which allows procurement through state owned entities under specific conditions, was applied despite the apparent lack of inhouse technology, expertise and resources necessary to independently execute the project.
Transparency International Pakistan noted that, at a prima facie level, the allegations appear credible and warned that the case could amount to “mis procurement” if substantiated under the applicable PPRA framework.
The watchdog also raised concerns over transparency issues, pointing out the alleged absence of key documents on the PPRA website. These include the evaluation report and the final contract agreement, both of which are mandatory disclosures under procurement rules.
Additional allegations cited in the complaint include violations related to beneficial ownership disclosures, inadequate price reasonability assessments and non compliance with performance bond requirements.
One of the most serious claims suggests that the contract may have been awarded at nearly double the prevailing market rate, raising the possibility of penalties under integrity pact provisions if any wrongdoing is proven.
Transparency International Pakistan has urged the Airports Authority to thoroughly investigate the matter and ensure that the project is retendered through an open and transparent bidding process in accordance with procurement laws.
The organisation clarified that it is not the original complainant but is acting as a whistleblower under Article 19A of the Constitution, which guarantees citizens the right to access information regarding public sector operations.
Copies of the letter have also been forwarded to key officials and institutions, including the Prime Minister’s adviser, the Ministry of Defence, the Public Procurement Regulatory Authority (PPRA), the National Accountability Bureau (NAB), the Federal Investigation Agency (FIA) and the Registrar of the Supreme Court, seeking action within their respective jurisdictions.