▫️Washington says the proposed US$1.25 billion loan remains under consideration as Pakistan finalises the project's revised financing structure
Islamabad | ReNews PakistanThe United States Export Import Bank (US EXIM Bank) will review its proposed US$1.25 billion financing package for Pakistan's Reko Diq copper and gold mining project after the project's overall costs are recalc...
The United States Export Import Bank (US EXIM Bank) will review its proposed US$1.25 billion financing package for Pakistan's Reko Diq copper and gold mining project after the project's overall costs are recalculated and the final financing structure is completed, according to officials at the US Embassy.
Speaking to a group of journalists, embassy officials said the financing proposal remains under active consideration and that the project continues to move forward despite progressing more slowly than originally anticipated. They explained that revisions to project costs and financing requirements have led to adjustments in the project's implementation timeline.
The Reko Diq project, located in Balochistan, is regarded as one of the world's largest undeveloped copper and gold deposits and is considered one of Pakistan's most strategically significant mining investments. The project is expected to play a major role in expanding the country's mineral exports, strengthening foreign exchange reserves and supporting long term economic growth.
Pakistan initially approved an investment plan of approximately US$6.7 billion for the first phase of the project. However, the federal government later approved revised definitive agreements and financial commitments, increasing the estimated first phase cost to approximately US$7.723 billion following updated technical and financial assessments.
US Embassy officials indicated that the proposed EXIM Bank financing forms part of a broader international funding framework being developed for the project. Other international financial institutions, including the International Finance Corporation (IFC), are also expected to participate in discussions on the project's final financing arrangements.
Officials emphasised that the recalculation of project costs should not be interpreted as a setback but rather as part of the normal process of finalising financing for a large scale mining development. They noted that major infrastructure and natural resource projects frequently undergo cost revisions before reaching financial close.
Once operational, Reko Diq is expected to become one of Pakistan's largest sources of mineral exports, creating thousands of direct and indirect employment opportunities while attracting additional foreign investment into the country's mining sector. The project is also expected to enhance Pakistan's position as a regional supplier of critical minerals that are increasingly important for clean energy technologies, electric vehicle batteries and advanced manufacturing industries.
The continued interest of international financial institutions and strategic partners reflects growing confidence in the long term commercial potential of the Reko Diq project and its importance for Pakistan's economic development strategy.