Published: July 29, 2026 - 2:50 PM
Audit Flags Serious Design and Safety Flaws in Islamabad’s Erdoğan Interchange Underpass
اسلام آباد کے طیب اردوان انٹرچینج میں سنگین ڈیزائن اور حفاظتی خامیوں کا انکشاف
▫️Auditor General says underpass geometry violates highway engineering standards, increasing safety risks for motorists and exposing consultant to potential liability
Islamabad | ReNews PakistanA recent audit conducted by the Auditor General of Pakistan has identified significant design deficiencies in the 9th Avenue/Jinnah Avenue Interchange, commonly known as the Recep Tayyip Erdoğan Interchange, wa...
A recent audit conducted by the Auditor General of Pakistan has identified significant design deficiencies in the 9th Avenue/Jinnah Avenue Interchange, commonly known as the Recep Tayyip Erdoğan Interchange, warning that the project poses a serious safety risk to motorists due to flaws in its geometric design.
The report concludes that the underpass loop incorporates a sharp 45 degree turn ending directly in front of a reinforced concrete wall, a layout that auditors say fails to comply with established transportation engineering standards.
According to the audit, the interchange loop was designed for a vehicle speed of approximately 30 kilometres per hour, despite the original feasibility study requiring a design speed of 60 kilometres per hour. Auditors observed that this substantial reduction in design speed without adequate mitigation measures creates a heightened risk of accidents and compromises road safety.
The feasibility study for the project, titled Resolving Traffic Congestion Issues at Crossing of 9th Avenue and Jinnah Avenue/Ibn e Sina Road, required that the interchange be designed in accordance with prevailing highway engineering standards and internationally accepted road safety principles. The audit states that the current design does not meet those requirements.
The report characterizes the issue as an example of gross professional negligence by the project’s design consultant. Under the consultancy agreement, the consultant was contractually obligated to deliver a design free from proven faults and technical errors. The agreement also empowers the Capital Development Authority (CDA) to recover financial losses resulting from design negligence, with compensation amounting to as much as twice the consultant’s design fee.
During a meeting of the Departmental Audit Committee held on January 8, 2026, CDA officials informed auditors that the consultant had submitted a detailed explanation regarding the interchange’s geometry and associated safety measures. The committee subsequently directed CDA management to obtain approval from the CDA Chairman before forwarding the consultant’s response to the audit authorities for review.
The latest observations follow earlier audit findings relating to the Bhara Kahu Bypass project, where auditors had also highlighted deficiencies including the absence of independent third-party design verification, failure to conduct the International Roughness Index (IRI) test to assess road quality, procurement violations, inadequate traffic management during construction, and non compliance with standard operating procedures.
Beyond the interchange project, the audit report highlights several financial and procurement irregularities across other CDA operations. These include payments of Rs 411.776 million under an extended solid waste disposal contract originally valued at Rs95.191 million, development contracts worth Rs 1.587 billion for Sector C-15 that auditors questioned over procedural compliance, and an additional payment of Rs341 million for work carried out at the F-10 roundabout beyond the approved project scope.
The report further notes unauthorized expenditure of Rs 7.134 million at Capital Hospital, where maintenance services for the oxygen generation plant continued after the expiry of the contract without initiating a fresh competitive bidding process.
According to the Auditor General, these cases collectively reflect weaknesses in contract administration, procurement oversight, financial controls, and project governance within the Capital Development Authority. The audit recommends corrective measures to strengthen compliance with procurement regulations, improve engineering oversight, and enhance accountability in the execution of public infrastructure projects.