CDA Says More Than 60% of Development Work Completed in Islamabad’s E-12

CDA Says More Than 60% of Development Work Completed in Islamabad’s E-12

▫️ Road and drainage work is progressing across E-12/1 to E-12/4 after the recovery of 1,135 kanals of government land

The Capital DevelIslamabad : ReNews City Reporter opment Authority (CDA) says more than 60 percent of development work in Islamabad’s Sector E-12 has been completed, as construction progresses across its four sub-sectors following the re...

The Capital Development Authority (CDA) says more than 60 percent of development work in Islamabad’s Sector E-12 has been completed, as construction progresses across its four sub-sectors following the recovery of 1,135 kanals of government land. In a press release issued on November 6, the authority said work was being accelerated under the directions of CDA Chairman and Islamabad Chief Commissioner Sohail Ashraf.

In E-12/4, earthwork has been completed, while construction of the road base and sub-base, along with the drainage system, is underway. Earthwork has also been completed on the Khayaban-e-Iqbal Service Road and the South and East service roads.
Progress is continuing in the other sub-sectors. In E-12/3, TST work has been completed in 15 streets, while earthwork and base construction are in progress in the remaining streets. In both E-12/1 and E-12/2, TST work has been completed in 25 streets, with work continuing on the remaining roads. Ashraf said the authority was removing obstacles to the sector’s development in accordance with the law. He said 1,135 kanals of government land, valued at billions of rupees, had been recovered after about four decades and that encroachments on public land would not be tolerated.

The CDA chairman said completing development work in E-12 and other sectors remained a priority, with available resources being used to speed up construction. The authority said the project would improve residential facilities and help meet Islamabad’s growing housing needs.
KDA Recovers Illegally Occupied Plot in Karachi’s Mehran Town During Anti Encroachment Operation

KDA Recovers Illegally Occupied Plot in Karachi’s Mehran Town During Anti Encroachment Operation

▫️ Karachi Development Authority removes unauthorised structures from Plot MB-71 in Sector 6-C, Korangi, and restores possession of allotted land

The Karachi Development Authority (KDA) has recovered Plot No.

Rawalpindi Launches Murree Road Repairs and Beautification Work Under Rs4 Billion Development Programme

Rawalpindi Launches Murree Road Repairs and Beautification Work Under Rs4 Billion Development Programme

▫️ Road rehabilitation begins from Faizabad to Liaquat Bagh, including repairs to 6th Road and Chandni Chowk flyovers

The Punjab Highway Department has initiated repair and rehabilitation work on Murree Road between Faizabad and Liaquat Bagh, including damaged sections of the 6th Road and Chandni Chowk flyovers.

SBCA Receives 17 Bids for Gul Plaza Demolition Project in Karachi

SBCA Receives 17 Bids for Gul Plaza Demolition Project in Karachi

▫️ Sindh Building Control Authority begins technical evaluation of contractors, with financial bids scheduled to open on November 24

Karachi | ReNews Sindh CorrespondentThe Sindh Building Control Authority (SBCA) has initiated the contractor selection process for the demolition of Gul Plaza in Karachi, receiving technical bids from 17 interested companies. The bids we...

Punjab Cabinet Committee Approves 13 Legislative and Privatisation Agenda Items, Focuses on Investment and Land Reforms

Punjab Cabinet Committee Approves 13 Legislative and Privatisation Agenda Items, Focuses on Investment and Land Reforms

▫️ Punjab government prioritises industrial infrastructure, modernisation of land records, investment promotion and faster implementation of development projects

The Punjab Cabinet Standing Committee on Legislative Affairs and Privatisation has approved all 13 agenda items during its 42nd meeting, chaired by Provincial Finance and Parliamentary Affairs Minister Mujtaba Shuja-ur-Rehman at the Civi...

Karachi Court Dismisses Property Ownership Suit, SHC Reserves Verdict in 53-Acre Land Dispute

Karachi Court Dismisses Property Ownership Suit, SHC Reserves Verdict in 53-Acre Land Dispute

▫️ Civil court rejects Wado Akharo Trust’s claim against federal government and Evacuee Trust Property Board over disputed property ownership

Karachi | ReNews Sindh CorrespondentA senior civil judge in Karachi South has dismissed a civil suit filed by Wado Akharo Trust against the federal government and others, declaring it not maintainable. The trust argued that the disputed ...

CDA Completes Over 68% Development Work in Islamabad’s Sector E 12, Continues Handover of Residential Plots

CDA Completes Over 68% Development Work in Islamabad’s Sector E 12, Continues Handover of Residential Plots

▫️ CDA retrieves 1,135 kanals of encroached land; Chairman Sohail Ashraf directs speedy completion of remaining development work.

The Capital Development Authority (CDA) has completed more than 68% of development work in Islamabad’s Sector E 12, where infrastructure development has remained delayed for nearly four decades.

Faisalabad Commissioner Reviews Urban Development Projects in Jhang, Calls for Public-Private Partnerships

Faisalabad Commissioner Reviews Urban Development Projects in Jhang, Calls for Public-Private Partnerships

▫️ District administration directed to ensure effective monitoring of development projects, improve the quality of public services and make efficient use of available resources.

Faisalabad Division Commissioner Dr Imran Hamid Sheikh visited Jhang on the directions of Punjab Chief Minister Maryam Nawaz Sharif to review ongoing urban development projects and public welfare initiatives.

Senate Panel Reviews Tourism Infrastructure Development at Taxila’s UNESCO Heritage Sites

Senate Panel Reviews Tourism Infrastructure Development at Taxila’s UNESCO Heritage Sites

▫️ Proposed development awaits UNESCO clearance by February 2027, with completion targeted for June 2028

Taxila | ReNews Regional CorrespondentThe Senate Standing Committee on National Heritage and Culture has reviewed proposed tourism infrastructure and conservation projects at Taxila’s UNESCO World Heritage sites.

Karachi Administration Reports Recovery of Nearly 290 Acres of Encroached Government Land

Karachi Administration Reports Recovery of Nearly 290 Acres of Encroached Government Land

▫️ Anti-Encroachment Force retrieves government and public amenity land across Malir, East, West and Korangi districts during 2026

The Karachi administration has reported the recovery of approximately 288 to 290 acres of government and public amenity land during anti-encroachment operations conducted across four districts in 2026.

CDA Says More Than 60% of Development Work Completed in Islamabad’s E-12

CDA Says More Than 60% of Development Work Completed in Islamabad’s E-12

▫️ Road and drainage work is progressing across E-12/1 to E-12/4 after the recovery of 1,135 kanals of government land

The Capital DevelIslamabad : ReNews City Reporter opment Authority (CDA) says more than 60 percent of development work in Islamabad’s Sector E-12 has been completed, as construction progresses across its four sub-sectors following the re...

The Capital Development Authority (CDA) says more than 60 percent of development work in Islamabad’s Sector E-12 has been completed, as construction progresses across its four sub-sectors following the recovery of 1,135 kanals of government land. In a press release issued on November 6, the authority said work was being accelerated under the directions of CDA Chairman and Islamabad Chief Commissioner Sohail Ashraf.

In E-12/4, earthwork has been completed, while construction of the road base and sub-base, along with the drainage system, is underway. Earthwork has also been completed on the Khayaban-e-Iqbal Service Road and the South and East service roads.
Progress is continuing in the other sub-sectors. In E-12/3, TST work has been completed in 15 streets, while earthwork and base construction are in progress in the remaining streets. In both E-12/1 and E-12/2, TST work has been completed in 25 streets, with work continuing on the remaining roads. Ashraf said the authority was removing obstacles to the sector’s development in accordance with the law. He said 1,135 kanals of government land, valued at billions of rupees, had been recovered after about four decades and that encroachments on public land would not be tolerated.

The CDA chairman said completing development work in E-12 and other sectors remained a priority, with available resources being used to speed up construction. The authority said the project would improve residential facilities and help meet Islamabad’s growing housing needs.
KDA Recovers Illegally Occupied Plot in Karachi’s Mehran Town During Anti Encroachment Operation

KDA Recovers Illegally Occupied Plot in Karachi’s Mehran Town During Anti Encroachment Operation

▫️ Karachi Development Authority removes unauthorised structures from Plot MB-71 in Sector 6-C, Korangi, and restores possession of allotted land

The Karachi Development Authority (KDA) has recovered Plot No.

Rawalpindi Launches Murree Road Repairs and Beautification Work Under Rs4 Billion Development Programme

Rawalpindi Launches Murree Road Repairs and Beautification Work Under Rs4 Billion Development Programme

▫️ Road rehabilitation begins from Faizabad to Liaquat Bagh, including repairs to 6th Road and Chandni Chowk flyovers

The Punjab Highway Department has initiated repair and rehabilitation work on Murree Road between Faizabad and Liaquat Bagh, including damaged sections of the 6th Road and Chandni Chowk flyovers.

SBCA Receives 17 Bids for Gul Plaza Demolition Project in Karachi

SBCA Receives 17 Bids for Gul Plaza Demolition Project in Karachi

▫️ Sindh Building Control Authority begins technical evaluation of contractors, with financial bids scheduled to open on November 24

Karachi | ReNews Sindh CorrespondentThe Sindh Building Control Authority (SBCA) has initiated the contractor selection process for the demolition of Gul Plaza in Karachi, receiving technical bids from 17 interested companies. The bids we...

Punjab Cabinet Committee Approves 13 Legislative and Privatisation Agenda Items, Focuses on Investment and Land Reforms

Punjab Cabinet Committee Approves 13 Legislative and Privatisation Agenda Items, Focuses on Investment and Land Reforms

▫️ Punjab government prioritises industrial infrastructure, modernisation of land records, investment promotion and faster implementation of development projects

The Punjab Cabinet Standing Committee on Legislative Affairs and Privatisation has approved all 13 agenda items during its 42nd meeting, chaired by Provincial Finance and Parliamentary Affairs Minister Mujtaba Shuja-ur-Rehman at the Civi...

Karachi Court Dismisses Property Ownership Suit, SHC Reserves Verdict in 53-Acre Land Dispute

Karachi Court Dismisses Property Ownership Suit, SHC Reserves Verdict in 53-Acre Land Dispute

▫️ Civil court rejects Wado Akharo Trust’s claim against federal government and Evacuee Trust Property Board over disputed property ownership

Karachi | ReNews Sindh CorrespondentA senior civil judge in Karachi South has dismissed a civil suit filed by Wado Akharo Trust against the federal government and others, declaring it not maintainable. The trust argued that the disputed ...

CDA Completes Over 68% Development Work in Islamabad’s Sector E 12, Continues Handover of Residential Plots

CDA Completes Over 68% Development Work in Islamabad’s Sector E 12, Continues Handover of Residential Plots

▫️ CDA retrieves 1,135 kanals of encroached land; Chairman Sohail Ashraf directs speedy completion of remaining development work.

The Capital Development Authority (CDA) has completed more than 68% of development work in Islamabad’s Sector E 12, where infrastructure development has remained delayed for nearly four decades.

Faisalabad Commissioner Reviews Urban Development Projects in Jhang, Calls for Public-Private Partnerships

Faisalabad Commissioner Reviews Urban Development Projects in Jhang, Calls for Public-Private Partnerships

▫️ District administration directed to ensure effective monitoring of development projects, improve the quality of public services and make efficient use of available resources.

Faisalabad Division Commissioner Dr Imran Hamid Sheikh visited Jhang on the directions of Punjab Chief Minister Maryam Nawaz Sharif to review ongoing urban development projects and public welfare initiatives.

Senate Panel Reviews Tourism Infrastructure Development at Taxila’s UNESCO Heritage Sites

Senate Panel Reviews Tourism Infrastructure Development at Taxila’s UNESCO Heritage Sites

▫️ Proposed development awaits UNESCO clearance by February 2027, with completion targeted for June 2028

Taxila | ReNews Regional CorrespondentThe Senate Standing Committee on National Heritage and Culture has reviewed proposed tourism infrastructure and conservation projects at Taxila’s UNESCO World Heritage sites.

Karachi Administration Reports Recovery of Nearly 290 Acres of Encroached Government Land

Karachi Administration Reports Recovery of Nearly 290 Acres of Encroached Government Land

▫️ Anti-Encroachment Force retrieves government and public amenity land across Malir, East, West and Korangi districts during 2026

The Karachi administration has reported the recovery of approximately 288 to 290 acres of government and public amenity land during anti-encroachment operations conducted across four districts in 2026.

More City and District Real Estate News

More Real Estate News

National Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →