PPIB Puts three 1,832MW  Hydropower Projects on Hold as Rooftop Solar Slows Electricity Demand Growth

PPIB Puts three 1,832MW Hydropower Projects on Hold as Rooftop Solar Slows Electricity Demand Growth

▫️Azad Pattan, Kohala and Kathai II projects face prolonged delays after failing to achieve financial close, while planners reassess their role under the IGCEP 2025 2035

Islamabad | ReNews PakistanThe Private Power and Infrastructure Board (PPIB) has decided to place three hydropower projects with a combined generation capacity of 1,832 megawatts on hold after determining that they no longer qualify unde...

Islamabad | ReNews Pakistan
The Private Power and Infrastructure Board (PPIB) has decided to place three hydropower projects with a combined generation capacity of 1,832 megawatts on hold after determining that they no longer qualify under the least cost optimisation framework of the Indicative Generation Capacity Expansion Plan (IGCEP) 2025 2035. The decision comes amid slowing electricity demand growth, which officials attribute largely to the rapid expansion of rooftop solar installations across the country.
According to observations made during the audit of the PPIB for the financial year 2024 25, the three projects 700.7MW Azad Pattan Hydropower Project, 1,124MW Kohala Hydropower Project and 8MW Kathai II Hydropower Project remained unimplemented after repeated delays in achieving financial close despite multiple extensions granted by the board.
The audit noted that the Letter of Support (LoS) for the Azad Pattan Hydropower Project was issued on June 30, 2016. However, the project failed to reach financial close by December 31, 2024, despite receiving five extensions, primarily because of financing constraints linked to China's export credit insurer, Sinosure.
The project sponsor later requested an additional extension until December 2027. During its 148th meeting held on August 1, 2025, the PPIB Board decided to maintain the existing status of the project while awaiting the outcome of the CPEC Energy Cooperation List Adjustment Joint Study. The board also noted that the project had not been selected under the draft IGCEP 2025–2035 least cost optimisation process.
Similarly, the Kohala Hydropower Project, which received its Letter of Support on December 31, 2015, has also been unable to achieve financial close despite several extensions that remain valid until September 30, 2027. Like Azad Pattan, the project was excluded from the draft IGCEP because it did not meet the revised least cost planning criteria.
The smallest of the three schemes, the 8MW Kathai II Hydropower Project, was issued its Letter of Support on November 20, 2019. However, the project encountered prolonged delays due to the non availability and delayed approval of standardised security package documents, which required clearance from the Economic Coordination Committee (ECC) and the Cabinet Committee on Energy (CCoE).
As a result, the PPIB Board approved the cancellation of the project's Letter of Support by mutual consent in August 2025. The audit observed that the cancellation highlighted broader regulatory and institutional facilitation gaps that were subsequently communicated to the relevant ministry in December 2025.
In its response to the audit, PPIB management stated that both the Azad Pattan and Kohala hydropower projects were excluded from the IGCEP 2025–2035 because of declining electricity demand projections driven by the rapid adoption of rooftop solar systems across Pakistan.
The development reflects a significant shift in the country's power sector planning, where changing consumption patterns, distributed renewable energy generation and least cost optimisation are increasingly influencing investment decisions for large scale electricity projects. While hydropower remains a key component of Pakistan's long term energy strategy, future project implementation is expected to depend on updated demand forecasts, financing availability and national generation planning priorities.
Rawalpindi: ETPB Provides Free Accommodation to Minority Students

Rawalpindi: ETPB Provides Free Accommodation to Minority Students

▫️ Apartment on Seventh Road handed over to 12 students; accommodation and essential facilities will be provided free of charge

The Evacuee Trust Property Board (ETPB) has handed over an apartment in Rawalpindi to provide accommodation for minority students.

Property Sale NOC to Be Withheld Over Unpaid Garbage Tax

Property Sale NOC to Be Withheld Over Unpaid Garbage Tax

▫️ Punjab links sanitation fee recovery to property transfers; 1.4 million bills distributed so far Second-quarter bills to be issued from January 1; some housing societies and towns exempt

The Punjab government has linked payment of the garbage tax, also known as the sanitation fee, to the issuance of a no-objection certificate (NOC) required for property transactions.

Punjab Horticulture Authority’s Reach Extended to All 41 Districts

Punjab Horticulture Authority’s Reach Extended to All 41 Districts

▫️ Notifications issued to establish district horticulture agencies in 20 districts, Administrative framework set up to oversee the province’s green spaces, says director general

The Punjab Horticulture Authority’s jurisdiction has been extended to all 41 districts of the province, establishing an administrative framework for the upkeep of green spaces across Punjab.

NEPRA Chairman Warns Power Division Agencies Over Delayed Data

NEPRA Chairman Warns Power Division Agencies Over Delayed Data

▫️ Missing deadlines in the second review could lead to an adverse decision or legal proceedings

NEPRA Chairman Waseem Mukhtar has urged agencies working under the Power Division to comply with the regulator’s directions, warning that continued delays in providing required information could jeopardise a package that requires upward ...

Tenders for 71 Development Projects Worth Rs 8.92bn Cancelled in KP

Tenders for 71 Development Projects Worth Rs 8.92bn Cancelled in KP

▫️ Communications and Works Department acts after allegations of kickbacks and politically driven project allocations

Tenders for 71 development schemes worth Rs 8.

More Than 70% of Karachi Buildings Fail Fire Safety Checks

More Than 70% of Karachi Buildings Fail Fire Safety Checks

▫️ Rescue 1122 says nearly 1,900 buildings were audited this year; officials cite weak enforcement, delayed emergency reporting and inadequate firefighting infrastructure

More than 70% of nearly 1,900 buildings inspected in Karachi since January have failed to meet required fire safety standards, raising concerns about the safety of thousands of people who live, work or study in them.

More Real Estate News

City and District Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →