Balochistan High Court Orders Sariab Road Flyover Redesign and Joint Road Traffic Survey
بلوچستان ہائی کورٹ کا سریاب روڈ فلائی اوور کا ڈیزائن ازسرنو تیار کرنے اور جوائنٹ روڈ کا ٹریفک سروے کرانے کا حکم
▫️ Proposed 600 metre flyover deemed insufficient, with a comprehensive design sought from the Geological Survey of Pakistan to the PTCL Exchange
Quetta | ReNews PakistanThe Balochistan High Court has directed authorities to reassess Quetta’s proposed Sariab Road flyover and prepare a comprehensive, technically practical design extending from the Geological Survey of Pakistan (GSP...
The Balochistan High Court has directed authorities to reassess Quetta’s proposed Sariab Road flyover and prepare a comprehensive, technically practical design extending from the Geological Survey of Pakistan (GSP) to the PTCL Exchange.
The court found that the proposed 600 metre flyover included in the provincial development programme for financial year 2026,27 would be insufficient to address traffic congestion along the corridor.
A bench comprising Chief Justice Muhammad Kamran Khan Mulakhail and Justice Muhammad Najmuddin Mengal reviewed the approved scheme and alternative proposals during proceedings on October 13, considering technical feasibility, costs and environmental implications.
For the section connecting the QDA office and Magsi Chowk towards GSP, the court directed improvements at ground level, including road widening and a suitable T junction.
The proceedings also considered whether alternative flyover designs would require the starting point to extend to Helper Hospital, potentially increasing costs and environmental impacts.
Officials informed the court that asphalt base course work had been completed along 14,500 metres of the 15,140 metre Sariab Service Road, equivalent to approximately 96 per cent. The asphalt wearing course had been laid along 8,500 metres, representing about 56 per cent.
Bridge construction was reported complete, while the stormwater drainage system was 98 per cent finished. Kerbstone and paver installation stood at 33 per cent. Authorities also reported obstacles affecting completion at some locations.
In separate proceedings concerning Joint Road, the court ordered a comprehensive traffic survey by the Balochistan Traffic Engineering Bureau in the presence of representatives from the Advocate General’s Office, Pakistan Railways and the petitioner. The Advocate General was appointed convener of the committee overseeing the exercise.
The court also sought a progress report on the flyover and associated development works.