Published: July 13, 2026 - 11:00 AM
Govt Allocates PKR 30 Billion for M 6 Motorway, Unveils Five Section Execution Plan to Accelerate Construction
حکومت نے ایم 6 موٹروے کیلئے 30 ارب روپے مختص کر دیے، تعمیر تیز کرنے کیلئے پانچ حصوں پر مشتمل منصوبہ پیش
▫️National Assembly Standing Committee told long delayed Sukkur Hyderabad Motorway will be developed through a mix of PPP, Islamic Development Bank and OPEC Fund financing
Islamabad | ReNews PakistanThe federal government has allocated PKR 30 billion in the current fiscal year for the long awaited Sukkur Hyderabad Motorway (M 6) and unveiled a comprehensive execution strategy aimed at accelerating construc...
The federal government has allocated PKR 30 billion in the current fiscal year for the long awaited Sukkur Hyderabad Motorway (M 6) and unveiled a comprehensive execution strategy aimed at accelerating construction by dividing the project into five sections with multiple financing arrangements.
The details emerged during a meeting of the National Assembly Standing Committee on Communications, chaired by Aijaz Hussain Jakhrani, where senior officials briefed lawmakers on the latest progress of the strategically important motorway project.
According to the briefing, the M-6 Motorway will be developed in five segments: Hyderabad–Tando Adam, Tando Adam Nawabshah, Nawabshah Naushahro Feroze, Naushahro Feroze Ranipur, and Ranipur Sukkur. The phased approach is intended to speed up implementation after the project remained stalled for more than five years.
Officials informed the committee that the motorway requires approximately PKR 70 billion during the current financial year, of which PKR 30 billion has already been allocated under the federal budget. Construction is expected to commence during the ongoing fiscal year as the government moves to revive one of Pakistan's most significant transport infrastructure projects.
The committee was further informed that different sections of the motorway will be financed through separate funding mechanisms. The Hyderabad Tando Adam and Tando Adam Nawabshah sections will be executed under the Public Private Partnership (PPP) model. The Naushahro Feroze Ranipur and Ranipur Sukkur sections will receive financial support from the Islamic Development Bank (IsDB), while the Nawabshah Naushahro Feroze section will be funded by the OPEC Fund for International Development (OFID).
During the meeting, officials also briefed lawmakers on the overall status of the Public Sector Development Programme (PSDP). They revealed that nearly PKR 2.6 trillion of the total PKR 3.7 trillion PSDP portfolio consists of throw forward projects, highlighting the substantial financial commitments carried over from previous years.
The committee was also informed that the National Highway Authority (NHA) had faced a reduction of approximately PKR 60 billion in its federal budget allocation due to government austerity measures and increased security related expenditures.
Expressing concern over limited funding for road maintenance in recent years, committee members directed the Ministry of Communications to submit a detailed report on the utilisation of maintenance funds, particularly for road networks in Sindh. The committee also sought updated progress reports on several delayed infrastructure schemes, including the Quetta Zhob Road, Keti Bandar Road, and the Shahdadkot Bypass, stressing the need for timely completion of projects vital to regional connectivity and economic development.