Published: June 27, 2026 - 10:00 AM
Peshawar Torkham Motorway Project Under Review as Estimated Cost Surges to PKR 130 Billion
پشاور طورخم موٹروے منصوبہ زیر غور، لاگت بڑھ کر 130 ارب روپے تک پہنچ گئی
▫️Government considers restructuring World Bank funded project after repeated bidding failures, while revised implementation plan divides expressway into three construction packages
Islamabad | ReNews PakistanThe federal government is reviewing the future of the Peshawar Torkham Motorway project following significant implementation delays and a sharp escalation in construction costs, prompting authorities to conside...
The federal government is reviewing the future of the Peshawar Torkham Motorway project following significant implementation delays and a sharp escalation in construction costs, prompting authorities to consider a comprehensive restructuring of the World Bank funded initiative.
The 47 kilometre access controlled motorway, being developed under the Khyber Pakhtunkhwa Economic Corridor (KPEC), was originally approved at an estimated cost of PKR 41.44 billion. However, updated projections have pushed the project's estimated cost to nearly PKR 130 billion, almost three times the original budget, leading policymakers to reassess its scope and execution strategy.
The project is financed through a USD 460 million loan agreement signed with the World Bank in December 2019. Although the financing became effective in June 2020 with a scheduled closing date of May 28, 2026, construction has yet to commence after more than five years due to repeated procurement and cost related challenges.
According to Planning Commission documents, the Central Development Working Party (CDWP) recently approved a working paper outlining a revised implementation framework. Under the updated proposal, the previously planned 55 kilometre Southern Link Road has been excluded from the project, while the main Peshawar Torkham Expressway will now be developed in three separate construction packages of approximately 14.3 kilometres, 15 kilometres and 15 kilometres.
The motorway has been planned as a four lane expressway linking Peshawar with the Torkham border crossing and forms an important component of the broader Peshawar Jalalabad Kabul motorway corridor. Once completed, the route is expected to strengthen Pakistan's regional trade links, improve cross border connectivity and facilitate the movement of goods between South Asia and Central Asia.
Officials said multiple bidding rounds had to be cancelled after contractors submitted bids that significantly exceeded the approved project cost and available loan financing. Planning authorities attributed the cost escalation to outdated estimates that were prepared using preliminary engineering designs and the National Highway Authority's Composite Scheduled Rates of 2014, which no longer reflect prevailing construction costs.
The Planning Commission further noted that the project's detailed engineering design is still under preparation. A revised PC I will be submitted after the completion of the detailed design, incorporating updated 2025 construction rates and revised financial estimates to ensure the project's long term viability.
Meanwhile, the government is engaged in discussions with the World Bank to secure an extension of the loan period, allowing sufficient time to implement the revised project plan and move forward with construction of one of Pakistan's most strategically significant transport corridors.