Published: October 5, 2026 - 10:01 AM
Rawalpindi Ring Road Cost Surges to Over Rs 53 Billion After Five Year Delay
پانچ سالہ تاخیر، راولپنڈی رنگ روڈ کی لاگت بڑھ کر 53 ارب روپے سے تجاوز کر گئی
▫️ Cost of 38.3 km six lane project more than doubles from initial Rs 22.82 billion as repeated delays and revisions add around Rs 30 billion to expenditure
Rawalpindi | ReNews PakistanThe cost of the Rawalpindi Ring Road project has surged to more than Rs 53 billion from an initial estimate of Rs 22.
The cost of the Rawalpindi Ring Road project has surged to more than Rs 53 billion from an initial estimate of Rs 22.82 billion, as repeated delays and revisions have left the major infrastructure scheme incomplete around five years after its launch.
The 38.3 kilometre, six-lane Ring Road project was awarded in March 2022 with the objective of improving traffic flow, strengthening regional connectivity and easing pressure on Rawalpindi’s existing road network.
However, delays in the project’s execution and subsequent revisions have pushed its cost up by around Rs 30 billion, taking the overall estimated expenditure beyond Rs 53 billion.
The Punjab government has announced several deadlines for completion of the project over the years, while preparations for its inauguration were reportedly made on two occasions. Despite these efforts, the road has yet to become fully operational.
Sources in the Rawalpindi Development Authority (RDA) said approximately 90 percent of construction work has now been completed and work on the remaining portions is progressing rapidly.
The prolonged delay and sharp escalation in cost have raised concerns over the financial burden on the public exchequer, particularly given the scale and strategic importance of the project. The Ring Road is regarded as one of the largest infrastructure projects undertaken in Rawalpindi.
Alongside construction delays and rising costs, the project has also faced scrutiny over alleged alterations to its original design.
An inquiry into the alleged design changes was launched in July, with Additional Chief Secretary Ahmed Raza Sarwar seeking the complete record of the project for examination.
Issues relating to No Objection Certificates (NOCs), approved layouts, access roads and other regulatory clearances have also become the subject of legal disputes, with some matters reaching the courts.
Questions surrounding alterations to the Ring Road’s original design first emerged in 2022 during the Pakistan Tehreek e Insaf government’s tenure. The controversy subsequently led to the transfer of then Rawalpindi Commissioner Muhammad Mehmood, Deputy Commissioner Anwar-ul-Haq and several other officials.
With most of the physical work now reported to have been completed, attention remains focused on the completion of the remaining construction, resolution of regulatory and legal issues and the final cost of a project whose estimated expenditure has more than doubled since its inception.