Published: November 4, 2026 - 1:01 PM
Rawalpindi Ring Road Opening Delayed by at Least Another Month
راولپنڈی رنگ روڈ کا افتتاح کم از کم ایک ماہ مزید تاخیر کا شکار
▫️ Toll plazas, eight weighing stations and electronic toll systems must be completed before the road opens to traffic
The opening of Rawalpindi Ring Road to traffic has been delayed by at least another month as construction continues on toll plazas and weighing stations, according to a senior district administration official.
The official said the provincial government would announce an inauguration date after the remaining facilities were completed. The work could take a month or longer, as construction and installation are still under way and procurement of weighing equipment has not been completed.
Authorities plan to establish eight weighing stations to measure heavy vehicles and calculate their toll charges. Construction is expected to take two to three weeks, after which teams will install the weighing machines. The Punjab Ring Road Authority will then need about two weeks to install the Intelligent Transportation System and Electronic Toll Collection system. Sensors will weigh trucks and determine the toll payable.
Toll plaza booths are also being built at Baanth and Thalian. The official said the road would open to both heavy and light traffic once the facilities became operational. Offices for the Punjab Ring Road Authority and residential accommodation for its officials are also being established.
Work on the Thalian interchange is expected to start after the road opens, with completion targeted for December, the official said.
The Ring Road has a design speed of 120 kilometres per hour, six lanes, controlled access, five interchanges and a 90-metre right of way. Its infrastructure includes bridges over the Soan and Sill rivers, 12 bridges across nullahs and roads, a railway bridge near Baanth and 11 overpasses.
The project’s original plan, developed during the PTI government, envisaged a 68-kilometre route. Work was halted following a financial scandal, after which authorities approved a revised 38.3-kilometre alignment from Baanth to Thalian.
Then-prime minister Imran Khan laid the project’s foundation stone in March 2022. The Pakistan Democratic Movement government later suspended the project temporarily, then authorized work after a third-party validation of the revised route.
Prime Minister Shehbaz Sharif laid the foundation stone at Rawat on August 8, 2023.