Published: August 4, 2026 - 11:09 AM
Why Were Expensive Power Plants Operated Outside the Economic Merit Order: Independent System and Market Operator
مہنگے پاور پلانٹس میرٹ آرڈر سے ہٹ کر کیوں چلائے گئے: انڈیپنڈنٹ سسٹم اینڈ مارکیٹ آپریٹر نے سوال اٹھا دیا
▫️ISMO’s report brings grid security and transmission constraints into focus, while plant wise generation and cost data are needed to calculate the actual financial impact
Islamabad | ReNews PakistanPakistan’s power system cannot always generate electricity strictly from the cheapest available plants. At times, relatively expensive plants have to be operated to keep the national grid secure, meet electrici...
Pakistan’s power system cannot always generate electricity strictly from the cheapest available plants. At times, relatively expensive plants have to be operated to keep the national grid secure, meet electricity demand in a particular area or manage limitations in the transmission network.
The Independent System and Market Operator issued its report on power plants operated under Security Constrained Economic Dispatch during June 2026 on July 31. ISMO also uploaded the latest Economic Merit Order, dated July 28, on July 29, 2026.
Under the Economic Merit Order, available power plants are ranked according to their incremental generation costs. In normal circumstances, cheaper plants are dispatched first, while progressively more expensive plants are brought online as electricity demand increases.
In actual grid operations, however, the cheapest plant may not always be located where electricity is immediately required. Limited transmission capacity, an outage at a grid station, voltage requirements, frequency stability, reserve needs or the unavailability of another generator may require the system operator to dispatch a plant placed lower in the merit order.
This process is known as Security Constrained Economic Dispatch. It aims to achieve the lowest possible generation cost without compromising the safety and reliability of the national grid. Operating a plant outside the pure economic order is therefore not necessarily a violation, but the technical reason, operating duration and financial impact should be clearly disclosed.
An additional cost arises when electricity from a higher-cost plant replaces power that could otherwise have been produced by a cheaper available generator. The estimated impact can be calculated by multiplying the difference between their per-unit costs by the electricity generated outside the normal merit order.
The July 28 merit order, however, is a later snapshot and cannot by itself establish the exact cost of dispatch decisions taken during June. A reliable calculation requires the merit order applicable on each relevant day in June, hourly plant generation, prevailing fuel prices, variable generation costs and evidence that a cheaper plant was available at the time.
The key public interest questions are whether the constraints recorded during June were unavoidable, how much electricity was generated by higher cost plants, how much additional cost was passed on to consumers and whether timely investment in the transmission system could have prevented such expenses.