Published: August 31, 2026 - 9:18 AM
CDWP Approves and Recommends Rs 60.259 Billion for Major Development Projects
سی ڈی ڈبلیو پی نے 60 ارب 25 کروڑ 90 لاکھ روپے کے بڑے ترقیاتی منصوبوں کی منظوری دیدی
▫️Gwadar Water Supply Scheme Gets Go Ahead for Bidding, While Karachi NeighbourhoodProject Awaits ECNEC Approval
Islamabad | ReNews PakistanThe Central Development Working Party (CDWP) has approved or recommended five major development projects with a combined estimated cost of Rs 60.259 billion, covering water supply, healthcare, road infrastructu...
The Central Development Working Party (CDWP) has approved or recommended five major development projects with a combined estimated cost of Rs 60.259 billion, covering water supply, healthcare, road infrastructure, higher education and urban development.
The decisions were taken at a CDWP meeting chaired by Federal Minister for Planning, Development and Special Initiatives Ahsan Iqbal, where development schemes from different parts of the country were reviewed. Of the five projects considered, three worth Rs 11.714 billion were approved by the CDWP, while two projects with a combined cost of Rs 48.545 billion were referred to the Executive Committee of the National Economic Council (ECNEC) for further consideration.
The largest project discussed was the Rs 29 billion Gwadar Town Water Supply Scheme, which aims to provide a sustainable water supply to Gwadar through water sourced from Mirani Dam. The project has also been referred to ECNEC.
Ahsan Iqbal directed the Balochistan government to examine an effective wastewater treatment mechanism for Gwadar alongside the water supply project. He stressed that untreated sewage must not be allowed to enter the sea, highlighting the environmental risks associated with the city's growing population and development activity.
The minister permitted the project to proceed towards the bidding stage, but made it clear that no contract should be awarded until ECNEC grants the required approval.
Among the projects approved directly by the CDWP is the establishment of a Medical and Nursing College in Gilgit, whose revised cost has been placed at Rs 4.924 billion. The project was originally initiated in 2017 but experienced delays, mainly because of funding constraints.
The planning minister emphasised the need to complete the long-delayed institution, which is expected to strengthen healthcare education and professional training opportunities in Gilgit-Baltistan.
The CDWP also approved the establishment of a National Defence University Faculty of Contemporary Studies (FCS) Campus at Defence Complex Islamabad, at an estimated cost of Rs 2.753 billion. The project is aimed at expanding the university's academic and research infrastructure.
Another approved scheme involves construction and improvement of a 53.4-kilometre road from Zera to Daboori in Orakzai District, with an estimated cost of Rs 4.037 billion. The road project dates back to 2016 and has faced delays over the years.
Ahsan Iqbal directed the relevant authorities to ensure that the remaining funds for the Orakzai road project are released before the onset of winter so that construction activity can continue and the long-pending scheme can move towards completion.
Meanwhile, the Rs 19.545 billion Karachi Neighbourhood Improvement Project was referred to ECNEC for further approval. The project is expected to be financed through foreign funding along with resources allocated under the Sindh government's development programme.
The latest CDWP decisions reflect the federal government's continued focus on infrastructure development, public-sector institutions, urban improvement and basic services. However, the projects referred to ECNEC will require the committee's approval before they can proceed to the next stage of implementation.