▫️Only 20.17% of revised financing disbursed; beneficiary led construction and demand side subsidies proposed to accelerate housing delivery
Islamabad | ReNews PakistanPunjab’s $200 million Affordable Housing Programme is facing a major implementation delay, with the World Bank proposing a 21 month extension that would push the programme’s completion date to March 2029.
Punjab’s $200 million Affordable Housing Programme is facing a major implementation delay, with the World Bank proposing a 21 month extension that would push the programme’s completion date to March 2029.
The programme, originally scheduled to close on June 30, 2027, has been affected by delays in the physical delivery of housing units. The World Bank has downgraded its implementation progress assessment to “Moderately Unsatisfactory” and raised the overall risk rating from Moderate to Substantial.
Approved in March 2022, the programme was designed to strengthen Punjab’s housing institutions and systems while expanding the supply and quality of affordable housing across the province.
The programme targets 77,000 housing units, including 37,000 affordable units. However, no affordable housing units had been delivered under the programme by May 2026, highlighting the gap between the programme’s targets and its implementation on the ground.
The programme’s revised financing stands at approximately $203.82 million, of which only $41.12 million, or 20.17%, had been disbursed. Around $162.70 million remained undisbursed.
To accelerate implementation, the proposed restructuring includes a beneficiary-led construction model, a demand-side subsidy window and expanded technical assistance.
The beneficiary-led approach would give eligible households a more direct role in constructing their homes, while the proposed subsidy mechanism is intended to improve access to affordable housing for eligible beneficiaries.
Several construction targets also remain outstanding, including 9,000 affordable units through the private sector, 8,000 through the public sector and 16,000 units for eligible beneficiaries.
Despite delays in physical construction, progress has been reported in developing the institutional and digital framework for the programme.
The Housing Market Information System (HMIS), Programme Management Information System (PMIS) and Beneficiary Management Information System (BMIS) have been developed and are operational. Location and infrastructure investment criteria have also been developed, approved and put into use.
Punjab has also taken regulatory steps to facilitate affordable private housing. The provincial Cabinet approved revised Affordable Private Housing Schemes Rules on June 25, 2024, while the PHATA Governing Body approved related regulations on April 17, 2025.
However, several key measures remain pending, including finalisation of eligibility criteria for Tier-1 beneficiaries, completion of costing and feasibility assessments for core housing designs, and processing of developer applications under the revised private housing framework.
The development of a comprehensive Punjab housing policy has also remained on hold pending notification and implementation of the federal government’s national housing policy.
The World Bank has identified technical design, institutional implementation capacity and sustainability as substantial risks to the programme.
The proposed extension and restructuring are aimed at moving the programme from institutional and regulatory preparation towards actual housing delivery, with a particular focus on expanding access to affordable homes for lower income and eligible households.