Rs 13 Billion Solar Project for More Than 45,000 Homes in Merged Districts Faces Further Delay as Federal Government Rejects PC-I
ضم شدہ اضلاع میں 13 ارب مالیت کا 45 ہزار سے زائد گھروں کا سولر منصوبہ مزید تاخیر کا شکار، وفاق نے پی سی ون مسترد کر دیا
▫️Technical, financial and administrative objections raised, with Khyber Pakhtunkhwa directed to revise and resubmit project documents
Peshawar | ReNews PakistanA Rs 13 billion solarisation project aimed at providing electricity to 45,887 households in Khyber Pakhtunkhwa’s merged districts has faced further delays after the federal government raised serious technical, f...
A Rs 13 billion solarisation project aimed at providing electricity to 45,887 households in Khyber Pakhtunkhwa’s merged districts has faced further delays after the federal government raised serious technical, financial and administrative objections to its PC-I and directed the provincial government to revise the project documents.
According to official records, the PC-I submitted by the Khyber Pakhtunkhwa government contained several shortcomings, preventing the project from moving forward for approval. The federal government had provided Rs 13 billion to the provincial government in 2024, yet solar systems have still not been distributed to eligible families.
The project is intended to provide affordable, environmentally friendly and sustainable electricity to thousands of households in the merged districts, particularly in areas where power supply remains limited or unreliable.
The matter was reviewed at a pre-Central Development Working Party meeting held on July 7, 2026, under the chairmanship of the Member Energy. The meeting examined progress on the Accelerated Implementation Plan and the proposed solar project.
Participants were informed that weak planning and incomplete documentation had prevented the project from meeting the required approval standards.
Earlier, at a meeting chaired by the Federal Minister for Planning on December 31, 2025, officials were directed to implement the scheme on a grant basis rather than through loans. The meeting also called for the appointment of qualified and experienced vendors and the use of Benazir Income Support Programme data to ensure the transparent identification of eligible households.
However, after reviewing the PC-I, the Energy Wing of the Planning Commission identified several deficiencies related to technical design, cost estimates, beneficiary selection, procurement procedures and project implementation.
Federal authorities have now directed the Khyber Pakhtunkhwa government to address all objections and prepare a revised PC-I before submitting the project again for approval.
The continued delay has raised concerns among thousands of families in the merged districts who have long struggled with inadequate electricity access and were expecting immediate relief through the solar scheme.